Offshore wind, grid, oil and gas, LNG, hydrogen and CCS projects. Each item carries its date and links to its source. Free to read, no sign-up.

Where work is coming.

Work announced at sea · Denmark

Horns Rev III

Period
31 Oct 2026 to 23 Dec 2026
Work
survey (temporary notice)
Sea area
DK: The North Sea
Announced
10 Nov 2026

Need people for this?

×

Planned stops at power stations

169 stops of 14 days or more in 12 countries over the next 12 months, plus 6 deratings. Most megawatts stand still in the week of 31 May 2027.

27.8 GWJan 27AprJulOct

Megawatts standing still, per week

Source: Elexon Insights, REMIT, Elia open data, ods202, Nord Pool UMM · 12 Nov 2026

A stop needs commissioning, I&C and turbine people.

Follow this areaTable

Work announced at sea

175 notices to mariners on 100 wind farms, fields and sea areas, November 2026 to April 2027.

676Nov355Dec196Jan148Feb142Mar108Apr

Notice-weeks per month

Source: Danish Maritime Authority, Niord notices to mariners, Kingfisher Information Service · 12 Nov 2026

Crew for one of these campaigns?

Follow this areaTable

Installation vessels, week of 5 to 11 Oct 2026

Daily positions of 65 of the 96 crane, cable, pipelay and jack-up vessels in the register. Satellite AIS runs ten days behind; this is a closed week, not live.

lying stillunder way

Source: Kystverket, Kystdatahuset (AIS) · 27 Oct 2026

Table

Helicopter passengers per base

Offshore helicopter passengers per month in Norway and the UK. On 11 Nov, 101 departures were planned from the six Norwegian bases; 66 flew.

  • Aberdeen23,618
  • Stavanger20,067
  • Bergen14,138
  • Kristiansund6,684
  • Norwich5,158
  • Sumburgh4,704
  • Florø2,418
  • Brønnøysund2,088
  • Blackpool2,102
  • Hammerfest1,494
  • Humberside925

Sep 2024Aug 2026

Passengers per month · figure: Aug 2026

Source: Statistics Norway (SSB), table 08507, UK Civil Aviation Authority, airport data table 19, Flight data from Avinor · 12 Nov 2026

Table

Workable days at sea

K13a wave buoy, Dutch North Sea, November 2026: 7 of 11 measured days with waves of 1.5 m or less from 07:00 to 19:00.

workablenotto come

Source: Rijkswaterstaat Waterwebservices, measured · 11 Nov 2026

Table

When are you needed? Your discipline and your date: the projects that start then

1. Pick what you follow

Follow companies, yards, areas and sectors.

Projects to watch
Companies & agencies
Yards
Areas
Sectors
Disciplines matched by our inference
Clear all

Latest

Awards, delays, new projects, tenders and permits, newest first. Follow something above to narrow the list.

2. Everything in the radar, newest first

  1. Milestone11 November 2026

    TenneT onshore cable installation nearing completion for Dutch offshore wind

    Underground electricity cable installation at Maasvlakte in Rotterdam progressing toward completion to connect three new offshore wind areas.

    Source: offshoreWIND.biz

  2. Permit11 November 2026

    Belgium relaunches Princess Elisabeth offshore wind tender with EU-approved subsidy

    European Commission approves EUR 2.04 billion state-aid scheme to support construction and operation of Belgium's first offshore wind farm.

    Source: offshoreWIND.biz

  3. Award11 November 2026

    ADES rigs secure multi-year ONGC contracts offshore India

    Two ADES jack-up rigs have been awarded multi-year contracts with Oil and Natural Gas Corporation for offshore operations in India.

    Source: Offshore Energy (Navingo)

  4. Milestone10 November 2026

    Southeast Asian offshore oil field starts production ahead of schedule

    An offshore platform in Vietnamese waters achieved first oil 36 days earlier than planned.

    Source: Offshore Energy (Navingo)

  5. Milestone10 November 2026

    Seabed monitoring systems installed at UK CCS project

    Six lander systems installed at Northern Endurance Partnership project to prepare for CO2 injection operations.

    Source: Offshore Energy (Navingo) · Project: Northern Lights CO2 transport & storage — Phase 2

  6. Award10 November 2026

    Odfjell Drilling secures seven-year rig contract with Vår Energi

    Odfjell Drilling has secured firm work for its semi-submersible rig through 2031 with options extending to 2035.

    Source: Offshore Energy (Navingo)

Show older items
  1. Award10 November 2026

    Njord Survey wins Energean decommissioning survey contract

    Njord Survey contracted by Energean for post-decommissioning surveys in the UK.

    Source: Offshore Energy (Navingo)

  2. Permit10 November 2026

    Murphy Oil awarded six Eastern Mediterranean offshore exploration licenses

    Murphy Oil secured six offshore exploration licenses in the Eastern Mediterranean near a major gas field.

    Source: Offshore Energy (Navingo)

  3. Award10 November 2026

    Dogger Bank B transmission assets: preferred bidder named

    Diamond Transmission UK and Chubu Electric Power selected as preferred bidder to acquire and operate Dogger Bank B offshore transmission assets.

    Source: Offshore Energy (Navingo) · Project: Dogger Bank B offshore wind farm

  4. Milestone9 November 2026

    Vard starts building third service vessel for Dong Fang

    Vard held keel-laying and coin ceremonies for NB 998, a commissioning service operation vessel for Dong Fang Offshore.

    Source: offshoreWIND.biz

  5. Award9 November 2026

    VIKING awarded €23.8M contract for seven patrol vessels

    VIKING Life-Saving Equipment Hellas signed a €23.8 million contract to build seven high-speed patrol vessels for the Hellenic Coast Guard.

    Source: Naval News

  6. Permit9 November 2026

    SSE Renewables gains grid consent for Berwick offshore wind phase

    SSE Renewables secured marine licence from UK MMO for export cable infrastructure of Berwick offshore wind project's third phase.

    Source: Offshore Energy (Navingo)

  7. Permit9 November 2026

    SSE Berwick Bank Phase 3 export cable licence granted

    SSE Renewables obtained marine licence from UK MMO for Berwick Bank offshore wind export cable infrastructure.

    Source: offshoreWIND.biz

  8. Award6 November 2026

    Worley awarded EPC contract for Venture Global LNG expansion

    Worley secured EPC duties for Venture Global's Louisiana LNG expansion project ahead of FID targeted for early 2027.

    Source: Offshore Energy (Navingo) · Project: Louisiana LNG expansion project

  9. Award6 November 2026

    Turkish firm wins offshore wind site survey contract

    DenAr Ocean Engineering Services awarded contract by Turkey's Ministry of Energy and Natural Resources for site investigation on the country's first offshore wind development.

    Source: Offshore Energy (Navingo)

  10. Award6 November 2026

    Tenaris wins tubular supply contract for Cyprus gas project

    Tenaris secured contracts to supply oil country tubular goods, line pipe and coating services for Cyprus's first commercial gas project.

    Source: Offshore Energy (Navingo) · Project: Cronos gas development — Block 6, offshore Cyprus

  11. Milestone6 November 2026

    Southeast Asian deepwater project reaches first gas

    A nearly $1-billion Southeast Asian deepwater development has achieved first gas production.

    Source: Offshore Energy (Navingo)

  12. Award6 November 2026

    Nexans wins cable supply contract for Greek HVDC link

    Nexans signed subcontract with Hellenic Cables and Asso.subsea to deliver 110 kV cable system for Corinth-Kos HVDC interconnection.

    Source: Offshore Energy (Navingo) · Project: Corinth-Kos HVDC

  13. Permit6 November 2026

    Vattenfall secures final agreements for Danish offshore wind farms

    Vattenfall and Danish Energy Agency signed final agreements for Hesselø and Holmsland offshore wind projects.

    Source: offshoreWIND.biz

  14. Milestone5 November 2026

    Vard begins building UPO’s second offshore wind service vessel in Vietnam

    Steel cutting has started for UPO’s second commissioning service vessel at Vard Vung Tau, Vietnam. The 88-metre hybrid vessel forms part of a two-vessel order supporting offshore wind work in Asia-Pacific.

    Source: offshoreWIND.biz

3. Your weekly digest

A preview, built from what is in the Radar now. The weekly digest carries only items added since the last one; with nothing new, no digest is sent.

Pick at least one follow; the digest preview appears here.

4. Get it by e-mail

We mail a confirmation link first. No account, no password.

We store your e-mail address and what you follow - nothing else, no open or click tracking. Unsubscribing deletes both. Privacy notice.

Demand per discipline, next 18 months.

Projects and stops in a phase that needs the role group, per month, in Northwest Europe. Not people.

Northwest EuropeRest of EuropeAmericasAfricaMiddle EastAsia-Pacific

Role groupNov 2026Dec 2026Jan 2027Feb 2027Mar 2027Apr 2027May 2027Jun 2027Jul 2027Aug 2027Sep 2027Oct 2027Nov 2027Dec 2027Jan 2028Feb 2028Mar 2028Apr 2028
Project management & controls5 announced· +136 estimated4 announced· +134 estimated4 announced· +134 estimated4 announced· +133 estimated4 announced· +133 estimated4 announced· +132 estimated4 announced· +130 estimated3 announced· +129 estimated3 announced· +127 estimated3 announced· +127 estimated3 announced· +124 estimated3 announced· +121 estimated3 announced· +48 estimated3 announced· +47 estimated3 announced· +38 estimated3 announced· +37 estimated3 announced· +22 estimated3 announced· +21 estimated
Engineering & design2 announced· +95 estimated2 announced· +95 estimated2 announced· +95 estimated2 announced· +95 estimated2 announced· +95 estimated2 announced· +95 estimated2 announced· +94 estimated2 announced· +94 estimated2 announced· +94 estimated2 announced· +94 estimated2 announced· +92 estimated2 announced· +90 estimated2 announced· +19 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +18 estimated2 announced· +4 estimated2 announced· +4 estimated
Construction & supervision33 announced· +40 estimated16 announced· +37 estimated13 announced· +37 estimated17 announced· +37 estimated26 announced· +37 estimated40 announced· +36 estimated64 announced· +35 estimated55 announced· +34 estimated51 announced· +32 estimated44 announced· +32 estimated39 announced· +32 estimated32 announced· +32 estimated16 announced· +30 estimated7 announced· +29 estimated2 announced· +21 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +17 estimated
Commissioning & start-up2 announced· +9 estimated1 announced· +9 estimated1 announced· +9 estimated1 announced· +8 estimated1 announced· +8 estimated1 announced· +8 estimated1 announced· +7 estimated+6 estimated+6 estimated+6 estimated+4 estimated
QA/QC & HSE4 announced· +42 estimated3 announced· +40 estimated3 announced· +40 estimated3 announced· +39 estimated3 announced· +39 estimated3 announced· +38 estimated3 announced· +37 estimated2 announced· +36 estimated2 announced· +34 estimated2 announced· +34 estimated2 announced· +33 estimated2 announced· +32 estimated2 announced· +30 estimated2 announced· +29 estimated2 announced· +21 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +17 estimated
Document control & support3 announced· +100 estimated3 announced· +100 estimated3 announced· +100 estimated3 announced· +100 estimated3 announced· +100 estimated3 announced· +100 estimated3 announced· +99 estimated3 announced· +98 estimated3 announced· +96 estimated3 announced· +96 estimated3 announced· +93 estimated3 announced· +91 estimated3 announced· +20 estimated3 announced· +20 estimated3 announced· +19 estimated3 announced· +19 estimated3 announced· +5 estimated3 announced· +5 estimated
announced: projects and stops with announced datesestimated: typical phase length, not announcedas of 2026-11-12
How we count

Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.

How the radar works.

One admission rule: an item must say where work is coming, for whom and when.

Sourced

Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is in our own words. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.

Admission

A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news is not admitted. Anything those checks cannot settle waits for a person.

Discipline matches are our inference

Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.