Poland's largest sanctioned offshore wind build (PLN ~27 bn) is mid-installation: substation topsides, cables and 100 turbines still go in during 2026–2027.
Offshore wind · Poland (Europe) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.
- Size
- 2 x 720 MW; 100 monopile foundations; first power 2027, COD 2028
- Operator / developer
- Equinor / Polenergia (joint venture)
- Phase, as reported
- installation (all 100 foundations and 2 substation jackets in place by August 2026; export cables being installed and brought ashore; substation topsides from winter 2026/27, turbines 2027)
- Checked on
- 2026-10-08
Phase track steps named in the reported phase are marked
- FID
- Engineering
- Fabrication
- Construction
- Installation
- Commissioning
Who builds it as stated by the sources
- Equinor — co-developer/owner
- Polenergia — co-developer/owner
- Heerema Marine Contractors — transport and installation of 100 monopiles, 100 transition pieces and two offshore substation jackets (SSCV Thialf; campaign completed Sept 2026); returns to install substation topsides (Bałtyk 2 winter 2026/27, Bałtyk 3 summer 2027)
- Siemens Gamesa — turbine supplier — 100 x 14.4 MW (per offshoreWIND.biz)
- Sif / Smulders — monopiles and transition pieces supply (per offshoreWIND.biz)
- Iemants (Smulders) — design and construction of the offshore substations (per offshoreWIND.biz)
Key dates as stated by the sources
- FID
- 2025-05-19
- Foundation campaign complete
- August 2026 (announced 3 September 2026)
- Turbine installation
- 2027
- First power
- 2027
- Full commercial operation
- 2028
Disciplines likely needed our inference
- offshore installation/T&I engineers
- WTG installation and commissioning technicians
- cable installation engineers
- HV substation commissioning
- marine coordination and HSE
Our inference from project kind and phase — not stated by the sources below.
On the Radar news about this project, each linked to its source
Sources checked on 2026-10-08
- All Foundations In Place at Bałtyk 2 & 3offshoreWIND.biz · published 2026-09-03 · retrieved 2026-09-22
- Equinor and Polenergia with contracts for transportation and installation of offshore wind farm foundations for Bałtyk 2 and 3Polenergia (company newsroom) · published 2024-07-03 · retrieved 2026-09-22
- Equinor and Polenergia take Final Investment Decisions (FIDs) for Bałtyk 2 and Bałtyk 3 offshore wind projectsPolenergia (company newsroom) · published 2025-05-19 · retrieved 2026-09-22
- Progress of workBałtyk 2 & 3 project site (Equinor/Polenergia) · published 2026-08 · retrieved 2026-10-08
Position on our globe: 54.85°N 17.00°E. Location approximate: Polish EEZ, Baltic Sea; Bałtyk 2 ~37 km and Bałtyk 3 ~22 km offshore near Ustka/Łeba; landfall near Ustka, O&M base in Łeba.