Radar · Projects to watch · 08 / 29
FPSO Gato do Mato (Shell) — Orca development
A Shell pre-salt FPSO in hull integration and topsides fabrication across Japanese and Chinese yards; delivery, installation and start-up targeted for 2029, then a 20-year MODEC O&M contract.
Deepwater FPSO · Brazil (Americas) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.
- Size
- 120,000 b/d FPSO; first oil 2029
- Operator / developer
- Shell Brasil
- Phase, as reported
- hull construction/integration (forward hull left Japan for China July 2026), topsides fabrication
- Checked on
- 2026-10-08
Phase track steps named in the reported phase are marked
- FID
- Engineering
- Fabrication
- Construction
- Installation
- Commissioning
Who builds it as stated by the sources
- Shell Brasil — operator (50%) and FPSO owner; partners Ecopetrol (30%) and KUFPEC (20%, acquired from Shell in Feb 2026, completion expected by end-2026 subject to approvals); PPSA manages the production sharing contract
- MODEC — FPSO purchase and sales agreement (design of hull and all topsides facilities) plus 20-year operations and maintenance contract (March 2025); multi-yard build with Sumitomo Heavy Industries (Yokosuka, forward hull) and COSCO Qidong (aft hull, integration)
- SOFEC (MODEC group) — spread mooring system
- Sumitomo Heavy Industries Marine & Engineering — forward hull block construction, Yokosuka (steel cut June 2025; block sailed to China July 2026)
- COSCO Qidong Shipyard — aft hull block (steel strike Oct 2025) and hull integration
Key dates as stated by the sources
- FID
- March 2025
- Modec contracts
- 2025-03-25
- Forward hull steel cut
- June 2025
- Aft hull steel strike
- October 2025
- Forward hull sailaway to china
- July 2026
- First oil target
- 2029
Disciplines likely needed our inference
- FPSO hull and topsides engineers
- yard construction supervision and QA/QC
- mooring and marine engineers
- commissioning and start-up engineers
- FPSO operations and maintenance staff
Our inference from project kind and phase — not stated by the sources below.
Sources checked on 2026-10-08
- MODEC Inks Purchase And Sales Agreement and Secures Operations and Maintenance Contract for Shell's Gato do Mato FPSO ProjectMODEC (company newsroom) · published 2025-03-25 · retrieved 2026-09-22
- MODEC: Pieces of Shell's Brazil-bound FPSO puzzle continue to slide into placeOffshore Energy · published 2025-10-06 · retrieved 2026-09-22
- MODEC Advances Construction of Brazil-Bound Gato do Mato FPSOBrazil Energy Insight · published 2026-07-02 · retrieved 2026-09-22
- Shell divests partial interest in Orca project offshore BrazilOffshore Magazine · published 2026-02-04 · retrieved 2026-10-08
- Forward Section of MODEC's Next Generation Hull for FPSO Gato do Mato Departs for Integration at China YardMODEC (company newsroom) · published 2026-07-02 · retrieved 2026-10-08
Position on our globe: 24.80°S 43.20°W. Location approximate: Santos Basin pre-salt, ~200 km south of Rio de Janeiro, water depth ~2,000 m.