Netherlands, United Kingdom, Germany, Denmark, Norway, Belgium and France: official schedules only. Rounds announced without dates are listed as announced. Grid and HVDC award rounds appear only where the TSO or regulator has published a schedule; most have not.
- Window
- closes 19 Apr 2024
- Award expected
- not published
- Authority
- DESNZ
- Capacity / scope
- not published
Shortlist of 27 electrolytic projects published 7 April 2025; the July 2025 market update expected awards in early 2026; no award announcement found on the gov.uk HAR2 pages on the check date.
Source
checked on 8 Oct 2026
- Window
- 16 Oct 2025 – 30 Oct 2025
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 1 GW
The October 2025 round closed without applications; RVO's planning table lists the new permit procedure for this site as to be determined.
On the North Sea map: Nederwiek wind farm zone, Nederwiek 1
Source
checked on 8 Oct 2026
- Window
- 20 Nov 2025 – 20 May 2026
- Awarded
- 4 Aug 2026
- Authority
- Energistyrelsen (Danish Energy Agency)
- Capacity / scope
- minimum 800 MW (0.8-1.2 GW depending on design)
Awarded on 2026-08-04 to Vattenfall Vindkraft Offshore Wind DK P/S at 542 DKK/MWh; the agency reports five bids; commissioning required by end of 2032.
Source
checked on 8 Oct 2026
- Window
- 20 Nov 2025 – 20 May 2026
- Awarded
- 4 Aug 2026
- Authority
- Energistyrelsen (Danish Energy Agency)
- Capacity / scope
- minimum 1 GW
Awarded on 2026-08-04 to Vattenfall Vindkraft A/S (on behalf of a company to be formed) at 504 DKK/MWh; the agency reports two bids; commissioning required by end of 2032.
Source
checked on 8 Oct 2026
- Window
- 20 Nov 2025 – 23 Oct 2028
- Award expected
- not published
- Authority
- Energistyrelsen (Danish Energy Agency)
- Capacity / scope
- minimum 1 GW
Tender opened 2025-11-20 together with Midt and Hesselø; bid deadline 2028-10-23; commissioning required by end of 2034; support cap of DKK 55.2 bn covers all three parks.
Source
checked on 8 Oct 2026
- Window
- 4 Dec 2025 – 19 Feb 2026
- Awarded
- 7 May 2026
- Authority
- European Commission (DG CLIMA) / CINEA
- Capacity / scope
- EUR 1.3 billion budget
Awarded on 7 May 2026: nine projects selected, four reserve projects invited in June 2026; grant agreement signature expected September-November 2026.
Source
checked on 8 Oct 2026
- Window
- 9 Dec 2025 – 24 Mar 2026
- Award expected
- not published
- Authority
- North Sea Transition Authority (NSTA)
- Capacity / scope
- 14 areas; up to 2 Gt CO2 storage potential
Applications closed 24 March 2026; NSTA aims to award licences in early 2027; five areas in Scottish and nine in English waters.
Source
checked on 8 Oct 2026
- Window
- not published
- Awarded
- 13 Jan 2026
- Authority
- Ministry of Energy / Norwegian Offshore Directorate
- Capacity / scope
- 57 production licences
Awarded on 13 January 2026: 19 companies were offered interests in 57 production licences.
Source
checked on 8 Oct 2026
- Window
- not published
- Awarded
- 14 Jan 2026
- Authority
- DESNZ / NESO
- Capacity / scope
- Pot 3 offshore wind projects totalling 8,245 MW and Pot 4 floating offshore wind 192.5 MW (sum of project sizes in the results notice)
Awarded on 2026-01-14: DESNZ published the Pot 3 and Pot 4 outcome as NESO notified applicants; ten fixed-bottom CfD units and two floating projects (Erebus, Pentland) listed.
Source
checked on 8 Oct 2026
- Window
- closes 4 Feb 2026
- Awarded
- 5 May 2026
- Authority
- Danish Energy Agency (Energistyrelsen)
- Capacity / scope
- 1.25 Mt CO2 per year awarded; budget approx. DKK 28 billion
Final bids due 4 February 2026; awarded on 5 May 2026 to Aalborg Portland for capture, transport and storage; support period 2029-2044.
Source
checked on 8 Oct 2026
- Window
- not published
- Awarded
- 3 Mar 2026
- Authority
- The Crown Estate
- Capacity / scope
- 1.5 GW (third site); up to 4.5 GW across three sites
Ocean Winds named for the third site on 2025-11-19 via direct award and entered the agreement for lease announced 2026-03-03; the other two sites (Equinor, Gwynt Glas) signed in October 2025.
Source
checked on 8 Oct 2026
- Window
- 5 May 2026 – 9 Sep 2026
- Award expected
- not published
- Authority
- BMWE
- Capacity / scope
- not published
Bidding ran 5 May to 9 September 2026 for participants of the preceding preparatory procedure; CCU/CCS technologies eligible; the ministry reports 21 bids; no award date published.
Source
checked on 8 Oct 2026
- Window
- 5 May 2026 – 1 Sep 2026
- Award expected
- Q1 2027
- Authority
- Ministry of Energy / Norwegian Offshore Directorate
- Capacity / scope
- not published
Announced 5 May 2026 for predefined areas in the North Sea, Norwegian Sea and Barents Sea; applications closed 1 September 2026 at 12:00; awards expected during the first quarter of 2027.
Source
checked on 8 Oct 2026
- Window
- Jun 2026 – 12 Oct 2026
- Award expected
- Feb 2027
- Authority
- Ministry in charge of energy (DGEC) / CRE
- Capacity / scope
- approx. 10 GW (approx. 5 GW fixed, approx. 5 GW floating)
Tender no. 1/2026 covers eleven projects off Normandy, Brittany, the South Atlantic coast and in the Mediterranean; projects first planned under AO9 were folded into AO10; bids due 12 Oct 2026 12:00 Paris time; CRE published amended specifications on 20 Aug, 24 Sep and 7 Oct 2026; ministry states award in February 2027.
Source
checked on 8 Oct 2026
- Window
- opens H2 2026
- Award expected
- not published
- Authority
- Ofgem
- Capacity / scope
- not published
Ofgem said on 2026-03-24 that Tender Round 14 is currently expected to begin in autumn 2026 and that the specific assets have not yet been confirmed; no launch notice or asset list was on Ofgem's OFTO tender rounds page on the check date.
Source
checked on 8 Oct 2026
- Window
- 20 Jul 2026 – 7 Aug 2026
- Award expected
- not published
- Authority
- DESNZ / NESO / LCCC
- Capacity / scope
- not published
Application window ran 20 July-7 August 2026; the indicative timetable puts NESO result notification between 27 Nov-1 Dec 2026 (no appeals) and 15-17 Feb 2027 (Tier 2 appeals), depending on the qualification scenario.
Source
checked on 8 Oct 2026
- Window
- 24 Jul 2026 – 4 Sep 2026
- Award expected
- Q4 2026
- Authority
- The Crown Estate
- Capacity / scope
- up to 1.5 GW
Accelerated re-tender of the Round 4 site discontinued in January 2026; offers a 10-year agreement for lease with the windfarm DCO (August 2025) and a NESO grid connection agreement in place. Open to sole bidders or consortia registered on The Crown Estate e-tendering portal; one questionnaire submission each, due 4 September 2026, decides entry to an ascending clock auction on a Site Exclusivity Fee paid over 20 years from lease. The 24 July notice was replaced on 27 July by a competitive flexible procedure notice with unchanged deadlines; Find a Tender gives 20 November 2026 as the estimated award decision date; The Crown Estate expects the auction and selection of a preferred bidder towards the end of 2026.
Source
checked on 8 Oct 2026
CCS & hydrogenannounced
Netherlands SDE++ 2026 application round (incl. CCS categories)
Netherlands · SDE++
- Window
- 27 Oct 2026 – 26 Nov 2026
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth
- Capacity / scope
- EUR 8 billion budget
RVO moved the round one month later than the 22 September-22 October window in the February 2026 letter to parliament; the letter sets the budget and adds CCS with low-carbon hydrogen and DAC categories.
Source
checked on 8 Oct 2026
- Window
- 26 Nov 2026 – 10 Dec 2026
- Award expected
- Q1 2027
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 1 GW
Permit with subsidy or a subsidy-free bid, both procedures run at the same time; maximum tender amount EUR 0.117 per kWh; RVO expects the wind farm to be operational in 2032.
On the North Sea map: IJmuiden Ver Gamma-A / Gamma-B wind farm sites, IJmuiden Ver Gamma
Source
checked on 8 Oct 2026
- Window
- 26 Nov 2026 – 10 Dec 2026
- Award expected
- Q1 2027
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 1 GW
Added to the 2026 round by government decision in April 2026; maximum tender amount EUR 0.116 per kWh; RVO expects the wind farm to be operational in 2032.
On the North Sea map: IJmuiden Ver Gamma-A / Gamma-B wind farm sites, IJmuiden Ver Gamma
Source
checked on 8 Oct 2026
- Window
- Dec 2026 – Feb 2027
- Award expected
- not published
- Authority
- European Commission (DG CLIMA) / CINEA
- Capacity / scope
- up to EUR 500 million budget (Topic 1: EUR 350 million RFNBO hydrogen; Topic 2: EUR 150 million RFNBO and/or electrolytic low-carbon hydrogen)
Commission plans to open the fourth auction in December 2026 and close it in February 2027; draft terms and conditions were published 9 July 2026 and the 7-week consultation concluded on 8 September 2026 with a webinar; final terms not yet published; Topic 2 admits electrolytic low-carbon hydrogen.
Source
checked on 8 Oct 2026
- Window
- opens 2027
- Award expected
- not published
- Authority
- Bundesnetzagentur / BSH
- Capacity / scope
- N-10.1 2,000 MW; N-10.2 500 MW; N-12.4 1,000 MW; N-12.5 1,000 MW; N-13.1 500 MW; N-13.2 1,000 MW (expected capacity per BSH site development plan)
Tenders planned for 2026 were moved to tender year 2027 after the cabinet decision of 28 Jan 2026; no bid date published; N-10.1 and N-10.2 received no bids on 1 Aug 2025. On 2 Sep 2026 the cabinet adopted a WindSeeG amendment bill (Bundestag Drucksache 21/8238, first reading 8 Oct 2026, not yet law): a two-stage award procedure (first subsidy-free, then a two-sided contract for difference), an annual tender corridor of 2,000-4,800 MW from 2027, a 35-year operating period, and the option for the site development plan to set a different bid date.
Source
checked on 8 Oct 2026
- Window
- opens H1 2027
- Award expected
- not published
- Authority
- The Crown Estate
- Capacity / scope
- approximately 6 GW or more
The Crown Estate intends to launch the round in the first half of 2027 after market engagement; capacity and sites remain subject to stakeholder engagement and NESO network plans.
Source
checked on 8 Oct 2026
- Window
- opens 2028
- Award expected
- not published
- Authority
- Bundesnetzagentur / BSH
- Capacity / scope
- N-6.8 2,000 MW; N-9.5 1,000 MW (expected capacity per BSH site development plan)
The amended site development plan of 30 Jan 2026 sets tender year 2028 for N-6.8 (moved from 2027) and N-9.5; no bid date published. A WindSeeG amendment bill adopted by the cabinet on 2 Sep 2026 (Drucksache 21/8238, not yet law) would introduce a two-stage subsidy-free/CfD award and a 2,000-4,800 MW annual corridor, and would form the basis for the next site development plan, which may re-cut sites.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- Federal Minister of Energy / FPS Economy / CREG
- Capacity / scope
- not published
Previous tender cancelled in early July 2025; on 18 Jul 2026 the Council of Ministers approved the amended tender royal decree (two-sided CfD, five-year build period, no strike price cap); launch follows Council of State advice and EU state aid notification, no launch date given.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 2 GW each
RVO's public planning table lists the tender/permit procedure for both sites as to be determined; the minister's 21 May 2026 letter to Parliament (Kamerstuk 33561, nr. 102) confirmed Doordewind kavel II's location in the development framework but left both kavels' delivery and tender dates unchanged pending the full roadmap update due end 2026.
On the North Sea map: Doordewind 1, Doordewind 2
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- not published
RVO states that the first offshore wind contracts for difference are planned to launch towards the end of 2027; no site or date published.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 1 GW (I-B); about 2 GW each (II, III)
RVO's planning table lists the permit procedure for these sites as to be determined.
On the North Sea map: Nederwiek wind farm zone, Nederwiek 2
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth
- Capacity / scope
- not published
RVO states preparations for offshore hydrogen production and transport are paused, citing the Climate and Energy Memorandum of 16 September 2025; no tender dates.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- Ofgem
- Capacity / scope
- not published
Ofgem published the pre-qualification shortlist of five bidders on 2026-03-24; Ofgem states the invitation-to-tender stage is due to commence during 2026 and gives no date for preferred-bidder selection, which follows each project's ITT evaluation.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- RVO / Ministry of Climate Policy and Green Growth (KGG)
- Capacity / scope
- about 0.7 GW each
RVO's planning table lists the permit procedure for both sites as to be determined; the roadmap map notes Ten noorden van de Waddeneilanden as a possible hydrogen demonstration site.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- DESNZ
- Capacity / scope
- not published
Government stated an aim to launch HAR3 by 2026 and HAR4 from 2028; no application window published.
Source
checked on 8 Oct 2026
- Window
- not published
- Award expected
- not published
- Authority
- Energidepartementet / NVE
- Capacity / scope
- up to 500 MW per project area
Two project areas were awarded on 2025-12-11; NVE held a hearing on the study programmes until 2026-06-18; a later competition gives state aid to one rights holder, no date published.
Source
- Utsira NordNVE (Norwegian Water Resources and Energy Directorate) · retrieved 20 Sep 2026
checked on 8 Oct 2026