SEAP-I and SEAP-II FPSOs (P-81, P-87) — Sergipe-Alagoas basin
Two more Fast4Ward-hull FPSOs entering SBM Offshore's record backlog right as Schiedam engineering ramps up — a multi-year pipeline of FPSO design, procurement and commissioning roles, on top of Jaguar and SBM's other current builds.
Deepwater FPSO · Brazil (Americas) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.
- Size
- Combined up to 240,000 bopd and 22 million m3/day gas; SEAP-II (P-87) alone: 120,000 bopd, 425 MMcfd gas treatment, 120,000 bpd water injection
- Operator / developer
- Petrobras
- Phase, as reported
- FIDs taken (SEAP-II late 2025, SEAP-I April 2026); SBM engineering and procurement started on both FPSOs (each <25% complete at H1 2026)
- Checked on
- 2026-10-08
Phase track steps named in the reported phase are marked
- FID
- Engineering
- Fabrication
- Construction
- Installation
- Commissioning
Who builds it as stated by the sources
- Petrobras — operator, FID holder
- SBM Offshore — build-operate-transfer contractor for both FPSOs; Petrobras will own the units, SBM operates for an initial 6.5 years
Reported risk as reported, as of 2026-10-08
Gas-export pipeline tender paused (September 2026). Petrobras has 'taken a step back' on the ~US$1 bn tender to assess Brazil's planned 'gas release' rules, which its E&P director had warned in July 2026 could delay the pipeline: a risk to the 2031 gas-export date rather than, so far, to the FPSO schedule.
Key dates as stated by the sources
- FID
- SEAP-II FID late 2025, SEAP-I FID April 2026; contracts signed by SBM Offshore late May 2026
- Startup target
- First oil targeted 2030, gas exports from 2031; SBM contractual handover SEAP-II (P-87) 2030, SEAP-I (P-81) 2031
Disciplines likely needed our inference
- topsides/process engineering
- project engineering/management
- procurement/estimating
- E&I
- commissioning (later phase)
Our inference from project kind and phase — not stated by the sources below.
Sources checked on 2026-10-08
- SBM Offshore signed contracts for Petrobras' FPSOs SEAP-I and SEAP-IISBM Offshore (company newsroom) · published 2026-05-29 · retrieved 2026-09-19
- Petrobras takes FID on SEAP FPSO development in Brazil basinWorld Oil · published 2026-04-14 · retrieved 2026-09-19
- Petrobras bringing $12-billion oil & gas project pair to life with SBM Offshore on FPSO duty for bothOffshore Energy · published 2026 · retrieved 2026-09-19
- SBM Offshore Half Year 2026 EarningsSBM Offshore (company newsroom / half-year report PDF) · published 2026-08-06 · retrieved 2026-10-08
- Petrobras 'dá um passo atrás' na licitação do gasoduto de SEAP para avaliar impactos do gas release, diz BaruzziABEGÁS (republishing eixos) · published 2026-09-29 · retrieved 2026-10-08
- Gas release pode atrasar projeto do gasoduto de SEAP, diz Petrobraseixos · published 2026-07-30 · retrieved 2026-10-08
- R$ 60 bilhões, duas plataformas e 32 poços: megaprojeto da Petrobras avança em Sergipe, mas gasoduto bilionário fica em esperaClick Petróleo e Gás · published 2026-10-03 · retrieved 2026-10-08
Position on our globe: 11.00°S 36.30°W. Location approximate: Sergipe-Alagoas basin, offshore northeastern Brazil (off Sergipe state); exact block coordinates not published in sources checked.