Radar · Projects to watch · 23 / 29
Mozambique LNG (Golfinho/Atum, Area 1)
A $20bn+ LNG project restarting at scale after a five-year security-driven suspension — a live test of how fast a paused megaproject can remobilise thousands of workers, and a rare African entry among 2026-2029 LNG builds. TotalEnergies said in September 2026 it could speed up a Phase 2 by keeping construction teams at Afungi.
LNG · Mozambique (Africa) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.
- Size
- 13 million tonnes/year (design)
- Operator / developer
- TotalEnergies (operator of the Mozambique LNG consortium)
- Phase, as reported
- construction (almost 45% complete as of July 2026; about 10,000 people on site by late September 2026)
- Checked on
- 2026-10-08
Phase track steps named in the reported phase are marked
- FID
- Engineering
- Fabrication
- Construction
- Installation
- Commissioning
Who builds it as stated by the sources
- TotalEnergies — operator, restarted project January 2026
- McDermott / Saipem / Chiyoda (EPC JV) — onshore LNG plant EPC consortium (contract predates the 2021 force-majeure suspension; consortium composition per trade press, not re-confirmed by a primary 2026 source in this check)
Reported risk as reported, as of 2026-10-08
Construction is operating in "containment mode" due to ongoing insurgency-related security concerns in Cabo Delgado; incremental costs from the suspension are reported at roughly $4.5 billion, pushing total investment above the original $20 billion. Equipment built in Middle East yards was held up by the 2026 regional conflict; TotalEnergies said in July 2026 that this had been resolved.
Key dates as stated by the sources
- Force majeure lifted
- 7 November 2025
- Full restart announced
- 29 January 2026
- First LNG target
- 2029
Disciplines likely needed our inference
- construction management
- piping/mechanical
- HSE (security-sensitive site)
- planning/project controls
- commissioning (later phase)
Our inference from project kind and phase — not stated by the sources below.
On the Radar news about this project, each linked to its source
Sources checked on 2026-10-08
- Mozambique LNG announces the full restart of all its activities onshore and offshore in MozambiqueTotalEnergies (company press release) · published 2026-01-29 · retrieved 2026-09-19
- TotalEnergies reboots $20 billion LNG project after years-long hiatusOffshore Energy · published 2026-01 · retrieved 2026-09-19
- TotalEnergies restarts $20bn LNG project in Mozambique after 5-year freezeAl Jazeera · published 2026-01-29 · retrieved 2026-09-19
- TotalEnergies 2Q2026 Earnings Call transcriptTotalEnergies (investor relations) · published 2026-07-23 · retrieved 2026-10-08
- Strategy and Outlook 2026 presentation (slides: upstream and integrated LNG project tables)TotalEnergies (investor presentation) · published 2026-09-28 · retrieved 2026-10-08
- TotalEnergies says Mozambique LNG Phase 2 could be acceleratedClub of Mozambique · published 2026-09-30 · retrieved 2026-10-08
- Mozambique LNG project 45% complete, first train on track for 2029, says TotalEnergiesClub of Mozambique · published 2026-08-03 · retrieved 2026-10-08
Position on our globe: 10.90°S 40.50°E. Location approximate: Afungi Peninsula, Cabo Delgado province.