Yggdrasil (Aker BP)

A three-platform development now estimated at NOK 195 bn (nominal, Oct 2026): the last topsides go offshore in late 2026, with hook-up, commissioning and subsea installation running into 2027.

Deepwater FPSO · Norway (Europe) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
~700 million boe; 57 wells on three platforms; 250 km power cable from shore
Operator / developer
Aker BP
Phase, as reported
offshore installation and hook-up (Hugin B topside installed early July 2026; Munin topside loaded out at Aibel Haugesund, ready for sail-away Aug 2026; Hugin A topside sail-away scheduled December 2026; power from shore commissioned June 2026)
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • Aker BP — operator (Hugin licence 76.72%); partners Equinor and Orlen Upstream Norway
  • Aker Solutions — EPC and offshore hook-up for the Hugin A production platform and jacket and the Hugin B unmanned wellhead platform and jacket (contract ~NOK 22 bn, Dec 2022); plus subsea production systems (~NOK 7 bn)
  • Subsea 7 — SURF package (per Offshore Technology project profile)
  • Allseas — topsides installation (per Offshore Technology project profile)
  • NKT — subsea power cables (per Offshore Technology project profile)
  • Aibel — EPC of the Munin unmanned production platform topsides (Haugesund)

Reported risk as reported, as of 2026-10-08

Cost growth: Norway's 2027 state budget (7 Oct 2026) puts Yggdrasil at NOK 195 bn nominal, up 9.8% in a year and from NOK 120.8 bn at PDO; Aker BP raised investment guidance in July 2026 to hold the 2027 start-up.

Key dates as stated by the sources

FID
December 2022
Pdo approval
June 2023
Hugin a first steel cut
September 2023
Hugin b topside sailaway
2026-07-06
Subsea final deliveries
2028 (per Aker Solutions 2022 release)
Startup target
2027 (Aker BP aims for summer 2027)
Hugin a topside sailaway
December 2026 (scheduled)

Disciplines likely needed our inference

  • offshore hook-up and commissioning engineers
  • subsea/SURF installation engineers
  • E&I and control systems engineers
  • structural/marine operations engineers
  • HSE and completion management

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. Aker BP sends Hugin B topside to Yggdrasil in the Norwegian North SeaPortNews · published 2026-07-06 · retrieved 2026-09-22
  2. Aker Solutions Secures Multiple Contracts with Aker BP – Record High Order IntakeAker Solutions (company newsroom) · published 2022-12-16 · retrieved 2026-09-22
  3. Yggdrasil Field Development, North Sea, NorwayOffshore Technology · retrieved 2026-09-22
  4. Aker BP increases project cost estimates to protect 2027 startupsOil & Gas Journal · published 2026-07-15 · retrieved 2026-10-08
  5. Aker BP narrows 2026 production guidance as major Norway projects advanceWorld Oil · published 2026-07-15 · retrieved 2026-10-08
  6. Mammoet completes critical topsides operations for Aker BP's Yggdrasil projectWorld Oil · published 2026-08-13 · retrieved 2026-10-08
  7. Costs of Aker BP's flagship offshore projects continue to rise (Reuters)Baird Maritime · published 2026-10-07 · retrieved 2026-10-08

Position on our globe: 59.90°N 2.20°E. Location approximate: Central North Sea, Norwegian shelf, ~160 km west of Kollsnes near Bergen; water depth 110–120 m.