Radar · Projects to watch · 26 / 29

Block B & 48/95, 52/97 gas development (Block B – O Mon gas-to-power)

A new offshore gas hub — central production platform, living-quarters platform, flare and bridges — fabricated in Vietnam under a McDermott-led EPCI contract, then installed and hooked up offshore.

Offshore gas platforms · Vietnam (Asia-Pacific) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
Gas for ~3,800 MW of power at O Mon; EPCI#1 >US$1 bn
Operator / developer
Phu Quoc Petroleum Operating Company (PQPOC) for Petrovietnam (PVN), with MOECO, PVEP, PV Gas and PTTEP as partners
Phase, as reported
fabrication / construction (EPCI#1 at ~29% overall progress with detailed engineering >71% as of August 2025; LQ fabrication underway)
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • McDermott — Consortium leader with PTSC for EPCI package #1: EPCI and hook-up/commissioning of the central production platform, living-quarters platform, flare tower and bridges (limited letter of award Oct 2023; full contract value >US$1 billion)
  • PTSC (Petrovietnam Technical Services Corporation) — Consortium partner on EPCI#1; PTSC M&C fabricating the living-quarter module (LQM, ~2,643 t) and living-quarter utility deck (LQU, ~3,236 t) — first cut August 2025, LQM load-out scheduled 24 February 2027
  • Vietsovpetro — Fabrication yard (VSP yard) named by PTSC for the living-quarter units

Reported risk as reported, as of 2026-10-08

First gas has moved from end-2026 to no later than Q3 2027, consistent with the February 2027 load-out of the living-quarters module. Downstream power plants lag: until end-2028 mainly O Mon I will be able to take Block B gas.

Key dates as stated by the sources

FID or award
EPCI#1 limited letter of award to McDermott–PTSC on 31 October 2023; consortium leading the package since October 2023
Milestone
LQM fabrication commenced 1 August 2025; LQM load-out scheduled 24 February 2027
Startup target
First gas from Block B no later than Q3 2027 (Government Office Notification 487/TB-VPCP, 15 September 2026); O Mon I commercial operation December 2027, O Mon IV December 2028, O Mon II Q4 2029, O Mon III May 2030 (Can Tho Department of Industry and Trade, October 2026)

Disciplines likely needed our inference

  • structural/topsides fabrication supervision
  • piping and E&I engineering
  • offshore installation and HUC
  • pipeline engineering
  • commissioning (gas processing, power)
  • project controls/planning
  • HSE

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. McDermott, PTSC Consortium Receives Limited Letter of Award for Block B Gas Development Project Offshore VietnamMcDermott (company newsroom) · published 2023-10-31 · retrieved 2026-09-22
  2. PTSC commences construction of LQM and LQU for the Vietnam Block B Gas ProjectPTSC (company news) · published 2025-08 · retrieved 2026-09-22
  3. Vietnam's gas-to-power project moves forward with planned investment nearing $12 billionOffshore Energy (trade press) · published 2024-06-04 · retrieved 2026-09-22
  4. Vietnam aims to fuel 3 power plants with Block B gas: PMThe Investor (Vietnam) · published 2024-05-13 · retrieved 2026-09-22
  5. Chuỗi dự án khí - điện Lô B - Ô Môn: Tiến độ của một mắt xích không thể tách khỏi toàn ChuỗiNăng lượng Việt Nam (Vietnam Energy Association journal) · published 2026-09-22 · retrieved 2026-10-08
  6. Chuỗi dự án khí - điện Lô B - Ô Môn và lịch tiến độ tích hợp các dự án thượng nguồn, trung nguồn, hạ nguồnNăng lượng Việt Nam · published 2026-09-24 · retrieved 2026-10-08
  7. Cần Thơ: Dòng khí Lô B dự kiến về năm 2027, các nhà máy Ô Môn vận hành từ cuối 2028Báo Xây dựng (Ministry of Construction newspaper) · published 2026-10-01 · retrieved 2026-10-08

Position on our globe: 7.90°N 103.20°E. Location approximate: Blocks B, 48/95 and 52/97 in the Malay–Tho Chu basin, southwest Vietnam continental shelf, ~77 m water depth, 300+ km offshore Ca Mau; gas piped ~400 km to the O Mon power complex at Can Tho. Exact CPP location not published in sources checked.