Radar · Projects to watch · 29 / 29

Oga–Katagami–Akita offshore wind farm (315 MW, Round 2)

First deployment of 15 MW-class turbines in Japan, installed by a DEME-affiliated jack-up in 2027; foundation, turbine installation and marine coordination work runs 2026–2028.

Offshore wind · Japan (Asia-Pacific) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
315 MW; 21 x Vestas V236-15.0 MW; commissioning June 2028
Operator / developer
Oga Katagami Akita Offshore Green Energy LLC — consortium of JERA, J-POWER, Tohoku Electric Power and Itochu
Phase, as reported
construction / pre-installation (turbine deliveries from 2026; offshore installation second half of 2027; full commissioning June 2028)
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • DEME (via Japan Offshore Marine JV) — Engineering works and vessel charter for offshore installation of the 21 wind turbines using the jack-up vessel Sea Challenger under Japanese flag; offshore works scheduled second half of 2027; DEME share up to ~EUR 50 million
  • Penta-Ocean Construction — Named alongside the project company as the contracting party for the turbine-installation package
  • Vestas — Turbine supplier: 21 x V236-15.0 MW (selected 2024; deliveries from 2026)
  • Kajima Corporation — manufacturing, procurement, transport and installation of the turbine foundations (contract October 2025)
  • JFE Engineering — manufactures and transports the 21 monopiles and transition pieces at its Kasaoka plant, January 2026 to March 2027; first monopile completed August 2026

Key dates as stated by the sources

FID or award
Development rights awarded end of 2023 (Round 2); DEME/JOM turbine-installation contract announced 29 May 2026
Milestone
First domestically made monopile completed August 2026; monopile/TP supply runs to March 2027; offshore turbine installation scheduled second half of 2027
Startup target
Full commercial operation June 2028 per trade press (reconfirmed July 2026, when the design received Bureau Veritas Japan certification)

Disciplines likely needed our inference

  • marine operations / installation engineering
  • WTG installation and commissioning technicians
  • client representatives / marine warranty
  • HV cable and substation engineering
  • HSE
  • package management

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. DEME wins contract for offshore wind project in JapanDEME (company newsroom) · published 2026-05-29 · retrieved 2026-09-22
  2. DEME to Install 15 MW Vestas Turbines at Japanese Offshore Wind FarmoffshoreWIND.biz · published 2026-05-29 · retrieved 2026-09-22
  3. JFE Engineering Rolls Out First 'Made in Japan' Monopile for Oga–Katagami–Akita Offshore Wind FarmoffshoreWIND.biz · published 2026-08-27 · retrieved 2026-10-08
  4. Japan's Oga–Katagami–Akita Offshore Wind Project Receives CertificationoffshoreWIND.biz · published 2026-07-22 · retrieved 2026-10-08
  5. Japan's first order received for domestic monopile production for large-scale offshore wind power project in general watersJFE Engineering (company newsroom) · published 2025-12-26 · retrieved 2026-10-08
  6. Kajima Inks Foundation Contract for 315 MW Japanese Offshore Wind FarmoffshoreWIND.biz · published 2025-10-23 · retrieved 2026-10-08

Position on our globe: 39.85°N 139.90°E. Location approximate: Off the coast of Oga, Katagami and Akita cities, Akita Prefecture, Sea of Japan side of Honshu. Exact turbine layout not published in sources checked.