Jansz-Io Compression (Gorgon gas supply)

A subsea-compression scheme keeping one of the world's largest LNG plants (Gorgon) supplied as its field ages — a rare, technically complex subsea-compression build with its own multi-year commissioning tail.

Subsea gas · Australia (Asia-Pacific) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
Maintains feed-gas supply to Gorgon LNG's three 15.6 MTPA trains via a 27,000-tonne floating field control station and ~6,500 tonnes of subsea compression infrastructure
Operator / developer
Chevron Australia (Gorgon joint venture)
Phase, as reported
installation / commissioning (Chevron's December 2024 indicative schedule runs installation from late-2024 to mid-2027; commissioning and start-up to commence from 2026/2027)
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • Chevron — operator
  • Saipem — contractor, ~$4bn order for the compression project scope

Reported risk as reported, as of 2026-10-08

Schedule has moved: Chevron's December 2024 update extended the installation window from mid-2024–mid-2026 to late-2024–mid-2027, with the compression station installed in two campaigns; no public start-up announcement found as of October 2026.

Key dates as stated by the sources

Sanctioned
2021 (project proceeded)
Startup target
Commissioning, start-up and operation expected to commence from 2026/2027 (Chevron operations environment plan, accepted by NOPSEMA 26 March 2026)

Disciplines likely needed our inference

  • subsea engineering
  • commissioning
  • controls/instrumentation
  • offshore installation supervision
  • HSE

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. Chevron's Jansz-Io compression project on trackOffshore Magazine · published 2024 · retrieved 2026-09-19
  2. Saipem wins contract for Chevron's Jansz-Io compression projectLNG Prime · published 2021-2022 · retrieved 2026-09-19
  3. Gorgon and Jansz Feed Gas Pipeline and Wells Operations (environment plan summary)NOPSEMA (Australian offshore regulator) · published 2024-12 · retrieved 2026-09-22
  4. Jansz-Io Compression Installation (information sheet, Dec 2024)Chevron Australia · published 2024-12 · retrieved 2026-10-08

Position on our globe: 20.75°S 115.40°E. Location approximate: Jansz-Io gas field / Barrow Island, offshore Western Australia.