GranMorgu (Block 58) FPSO development

Suriname's first large offshore oil development (US$12.2 bn): FPSO construction, ~190 km of subsea lines and an installation campaign running out of Paramaribo through 2027–2028.

Deepwater FPSO · Suriname (Americas) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
220,000 b/d FPSO; ~190 km subsea lines; first oil mid-2028
Operator / developer
TotalEnergies EP Suriname
Phase, as reported
FPSO construction (SBM: >50%-<75% complete at H1 2026; Fast4Ward hull launched out of second dry dock, topsides fabrication continuing) and subsea installation campaign started June 2026
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • TotalEnergies — operator; partners APA Corporation and Staatsolie (40/40/20 per Ocean Energy Resources, June 2026)
  • SBM Offshore — construction and installation of the FPSO in partnership with Technip Energies, plus operations and maintenance after deployment (Nov 2024)
  • Technip Energies — FPSO EPC partner of SBM Offshore (per SBM Offshore release)
  • TechnipFMC — integrated EPCI (iEPCI) for subsea systems — Subsea 2.0 trees, manifolds, connectors, topside controls, umbilicals, flexible jumpers and flexible risers
  • Saipem — EPCI of the SURF package (~US$1.9 bn): ~100 km production flowlines, ~90 km injection lines, T&I of flexible risers, umbilicals and structures; offshore operations started June 2026 from Paramaribo with MCV Normand Navigator

Reported risk as reported, as of 2026-10-08

No schedule slippage reported. Staatsolie's 20% stake (est. US$2.4 bn) is funded through a US$1.6 bn bank loan from 18 lenders (signed 14 May 2025) plus own cash, cash flow and March 2025 bond proceeds; about half of the ~US$12 bn capex had been spent by September 2026.

Key dates as stated by the sources

FID
2024-10-01
Main contract awards
2024-11-14
Saipem offshore operations start
2026-06-24
First oil target
mid-2028

Disciplines likely needed our inference

  • FPSO topsides and hull engineers
  • SURF/pipeline installation engineers
  • subsea controls and commissioning
  • marine base logistics and HSE
  • FPSO operations and maintenance staff

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. SBM Offshore awarded contracts for the GranMorgu field developmentSBM Offshore (company newsroom) · published 2024-11-14 · retrieved 2026-09-22
  2. TotalEnergies awards FPSO, subsea contracts for GranMorgu project offshore SurinameOffshore Magazine · published 2024-11-14 · retrieved 2026-09-22
  3. Saipem starts operations GranMorgu project in SurinameOcean Energy Resources · published 2026-06-24 · retrieved 2026-09-22
  4. SBM Offshore's Suriname-bound FPSO for TotalEnergies $12.2B oil project starts taking shapeOffshore Energy · published 2025-05-12 · retrieved 2026-09-22
  5. SBM Offshore Half Year 2026 EarningsSBM Offshore (company newsroom / half-year report PDF) · published 2026-08-06 · retrieved 2026-10-08
  6. TotalEnergies' offshore project in Suriname on track for first output in mid-2028Pipeline & Gas Journal · published 2026-09-20 · retrieved 2026-10-08
  7. Staatsolie and the GranMorgu Project backed by broad (inter)national confidenceStaatsolie (company newsroom) · published 2025-05-14 · retrieved 2026-10-08
  8. Suriname offshore oil and gas momentum builds as GranMorgu advancesWorld Oil · published 2026-08-13 · retrieved 2026-10-08

Position on our globe: 7.30°N 55.60°W. Location approximate: Block 58, ~150 km offshore Suriname; FPSO in ~400 m water depth, subsea scope in 100–1,100 m.