Radar · Projects to watch · 20 / 29

North Field East and North Field South LNG expansion

The single largest LNG capacity build-out under way anywhere, with Technip Energies — a company legally headquartered in the Netherlands — as lead EPC contractor on both expansion phases; years of engineering, commissioning and construction-supervision demand still ahead as later trains follow NFE Train 1.

LNG · Qatar (Middle East) · every fact below is as reported by the linked sources, checked by hand on 2026-10-08.

Size
North Field East + South together raise Qatar's LNG capacity from 77 to 126 MTPA by ~2027-2028
Operator / developer
QatarEnergy
Phase, as reported
construction / commissioning (first NFE train ready to start operation in November 2026; remaining NFE trains and NFS under construction after a war-related work suspension in early 2026)
Checked on
2026-10-08

Phase track steps named in the reported phase are marked

  1. FID
  2. Engineering
  3. Fabrication
  4. Construction
  5. Installation
  6. Commissioning

Who builds it as stated by the sources

  • QatarEnergy — operator/developer
  • Technip Energies — EPCC contractor (with Chiyoda) for North Field East onshore facilities — 4 mega-trains of 8 MTPA each; also working NFS with CCC
  • Chiyoda Corporation — EPCC joint-venture partner with Technip Energies on North Field East
  • CCC (Consolidated Contractors Company) — partner with Technip on North Field South

Reported risk as reported, as of 2026-10-08

War-related work stop in early 2026. Iranian strikes on Ras Laffan and Mesaieed halted NFE/NFS work and damaged two existing LNG trains (about 17% of Qatar's capacity, repairs up to three years); disrupted shipping through the Strait of Hormuz makes the timing of later NFE trains uncertain.

Key dates as stated by the sources

NFE full startup
Uncertain — timing of later NFE trains depends on shipping through the Strait of Hormuz
NFS startup target
H2 2028
NFE startup
First NFE train ready to start operation November 2026; first LNG expected Q1 2027 (QatarEnergy CEO: first half of 2027)

Disciplines likely needed our inference

  • piping/mechanical engineering
  • construction supervision
  • commissioning
  • planning/project controls
  • QA/QC

Our inference from project kind and phase — not stated by the sources below.

Sources checked on 2026-10-08

  1. Technip Energies and Chiyoda Awarded a Major LNG Contract for the North Field East Project in QatarTechnipFMC / Technip Energies (company press release) · published 2020s (original award) · retrieved 2026-09-19
  2. QatarEnergy North Field East (NFE)Technip Energies (company case study) · published 2026 · retrieved 2026-09-19
  3. QatarEnergy's North Field West LNG Project Startup Slips to 2031Natural Gas Intelligence · published 2026 · retrieved 2026-09-19
  4. QatarEnergy's LNG expansion project poised to start operations in November, sources say (Reuters)BOE Report · published 2026-10-07 · retrieved 2026-10-08
  5. QatarEnergy suspends work on North field expansion due to US-Iran conflictOffshore Magazine · published 2026-03-02 · retrieved 2026-10-08
  6. QatarEnergy Warns Shipping Snags Threaten LNG RoadmapTradingpedia · published 2026-09-21 · retrieved 2026-10-08

Position on our globe: 25.90°N 51.55°E. Location approximate: Ras Laffan Industrial City, Qatar.