YRproject Radar

Awards, tenders, start-ups and delays, worldwide.

Offshore wind, grid, oil and gas, LNG, hydrogen and CCS projects. Each item carries its date and links to its source. Free to read, no sign-up.

Where work is coming.

Work announced at sea · Norway

STJERNE (platform)

Period
14 Sep 2026 to 11 Dec 2026
Work
drilling (rigs & anchors)
Sea area
Northern North Sea
Announced
16 Oct 2025

Need people for this?

×

Planned stops at power stations

167 stops of 14 days or more in 12 countries over the next 12 months, plus 5 deratings. Most megawatts stand still in the week of 31 May 2027.

26.2 GWOctJan 27AprJulOct

Megawatts standing still, per week

Source: Elexon Insights, REMIT, Elia open data, ods202, Nord Pool UMM · 24 Oct 2026

A stop needs commissioning, I&C and turbine people.

Follow this areaTable

Work announced at sea

183 notices to mariners on 107 wind farms, fields and sea areas, October 2026 to March 2027.

699Oct563Nov291Dec153Jan120Feb115Mar

Notice-weeks per month

Source: Danish Maritime Authority, Niord notices to mariners, Kingfisher Information Service · 24 Oct 2026

Crew for one of these campaigns?

Follow this areaTable

Installation vessels, week of 5 to 11 Oct 2026

Daily positions of 65 of the 96 crane, cable, pipelay and jack-up vessels in the register. Satellite AIS runs ten days behind; this is a closed week, not live.

lying stillunder way

Source: Kystverket, Kystdatahuset (AIS) · 24 Oct 2026

Table

Helicopter passengers per base

Offshore helicopter passengers per month in Norway and the UK. On 23 Oct, 75 departures were planned from the six Norwegian bases; 65 flew.

  • Aberdeen23,618
  • Stavanger17,228
  • Bergen14,215
  • Kristiansund5,964
  • Norwich5,158
  • Sumburgh4,704
  • Florø2,175
  • Brønnøysund2,588
  • Blackpool2,102
  • Hammerfest1,330
  • Humberside925

Sep 2024Aug 2026

Passengers per month · figure: Aug 2026

Source: Statistics Norway (SSB), table 08507, UK Civil Aviation Authority, airport data table 19, Flight data from Avinor · 24 Oct 2026

Table

Workable days at sea

K13a wave buoy, Dutch North Sea, October 2026: 8 of 23 measured days with waves of 1.5 m or less from 07:00 to 19:00.

workablenotto come

Source: Rijkswaterstaat Waterwebservices, measured · 23 Oct 2026

Table

When are you needed? Your discipline and your date: the projects that start then

1. Pick what you follow

Follow companies, yards, areas and sectors.

Projects to watch
Companies & agencies
Yards
Areas
Sectors
Disciplines matched by our inference
Clear all

Latest

Awards, delays, new projects, tenders and permits, newest first. Follow something above to narrow the list.

2. Everything in the radar, newest first

  1. Milestone23 October 2026

    FSO achieves first oil ahead of schedule offshore Vietnam

    Yinson Production and PTSC reached first oil at an FSO vessel deployed offshore Vietnam ahead of schedule.

    Source: Offshore Energy (Navingo)

  2. Award23 October 2026

    Balfour Beatty awarded substation contract for Dogger Bank wind farms

    Balfour Beatty contracted by National Grid to deliver first phase of Birkhill Wood 400 kV substation in East Yorkshire for Dogger Bank wind farm connection.

    Source: offshoreWIND.biz · Project: Birkhill Wood 400 kV substation

  3. Award22 October 2026

    DOF secures subsea installation contract in Africa for 2027

    DOF Group won a subsea installation contract in Africa for 100 days of vessel work in early 2027.

    Source: Offshore Energy (Navingo)

  4. Milestone21 October 2026

    Infill drilling underway offshore Oman, production targeted for November 2026

    Masirah Oil has commenced infill well drilling at an offshore Oman oil field with production expected by November 2026.

    Source: Offshore Energy (Navingo)

  5. Award21 October 2026

    Diverse Marine wins order for three crew transfer vessels

    UK shipbuilder Diverse Marine secured an order from OEG Marine Services for three additional crew transfer vessels.

    Source: offshoreWIND.biz

  6. Milestone20 October 2026

    STM lays keel for Portugal's second logistics support ship

    STM held keel-laying ceremony for the second logistics support ship ordered by the Portuguese Navy in Istanbul.

    Source: Naval News

Show older items
  1. Award20 October 2026

    Técnicas Reunidas wins LNG Canada Coastal GasLink Phase 2 EPCM contract

    Técnicas Reunidas awarded €200M+ EPCM contract for LNG Canada's Coastal GasLink Phase 2 project.

    Source: Offshore Energy (Navingo) · Project: Coastal GasLink Phase 2

  2. Permit20 October 2026

    New Zealand opens offshore wind feasibility permit round

    New Zealand has opened a feasibility permit application round for offshore wind developers to investigate potential sites.

    Source: offshoreWIND.biz

  3. Award20 October 2026

    EU funds Aker BP and Höegh Evi CO2 transport storage project

    Aker BP and Höegh Evi received €223 million from the European Union Innovation Fund for a large-scale CO2 transport and storage project.

    Source: Offshore Energy (Navingo)

  4. Award19 October 2026

    Wood Thilsted awarded design contract for Outer Dowsing monopiles

    Wood Thilsted secured a contract for detailed design of up to 100 monopile foundations for the 1.5 GW Outer Dowsing offshore wind farm.

    Source: offshoreWIND.biz · Project: Outer Dowsing offshore wind farm

  5. Award19 October 2026

    Transocean drillships secure $550M US Gulf contracts

    Transocean awarded multi-well ultra-deepwater contracts for two drillships in the U.S. Gulf extending through 2027.

    Source: Offshore Energy (Navingo)

  6. Award19 October 2026

    Taiwan orders MARTAC autonomous boats with production in Florida and Taiwan

    Taiwan’s Coast Guard is buying MARTAC T24 unmanned vessels. The acquisition announced on 19 October provides for production in Florida and Taiwan; vessel numbers and delivery dates were not disclosed.

    Source: Naval News · Project: Devil Ray T24

  7. Award19 October 2026

    Minesto selected for Irish tidal-array grant; agreement expected in Q1 2027

    The EU selected Minesto’s planned 10 MW Euro Dragon Farm in Irish waters for a EUR 20.2 million grant. Agreement preparation is under way, with signing expected in Q1 2027; construction approval is not implied.

    Source: Offshore Energy (Navingo) · Project: Euro Dragon Farm

  8. Award19 October 2026

    EU selects 77 net-zero projects for €3.4bn in Innovation Fund support

    The European Commission selected 77 net-zero technology projects across 23 EEA countries for €3.4bn in Innovation Fund support on 19 October. The selection covers industrial decarbonisation, renewables and clean-tech manufacturing.

    Source: European Commission - press corner

  9. Milestone17 October 2026

    Indian Navy commissions L&T-built Samarthak as a trials and unmanned-systems platform

    The Indian Navy commissioned L&T-built INS Samarthak at Karwar on 16 October. The multi-purpose vessel enters service as a platform for weapons and sensor trials, unmanned-system operations and maritime surveillance.

    Source: Naval News

  10. Milestone16 October 2026

    Prospector 5 mobilises for four-well MaBoMo production campaign off Gabon

    Borr Prospector 5 is mobilising to the MaBoMo platform for BW Energy’s Dussafu development off Gabon. The planned Phase 2 campaign covers four production infill wells at Hibiscus and Hibiscus South, with the first new well expected on stream in early 2027.

    Source: Offshore Energy (Navingo)

  11. Award16 October 2026

    Mari Energies awards EMGS offshore survey work in Pakistan

    EMGS received a letter of award from Mari Energies for electromagnetic data acquisition across offshore exploration blocks in Pakistan. The 16 October report gives no mobilisation date or contract value.

    Source: Offshore Energy (Navingo)

  12. Milestone16 October 2026

    Taiwan's Hai Long offshore wind farm fully operational

    All 73 turbines at the 1,022 MW Hai Long offshore wind project in Taiwan are installed and generating electricity.

    Source: offshoreWIND.biz

  13. Award15 October 2026

    VicGrid chooses Acciona to develop Gippsland offshore-wind grid link

    Acciona is VicGrid’s preferred development partner for the link serving the first 2 GW of offshore wind off Gippsland. Design and procurement precede a final construction offer; completion is targeted for 2031.

    Source: offshoreWIND.biz · Project: Gippsland offshore-wind grid link

  14. Award15 October 2026

    TMC wins air-system package for Brazil-bound Maromba FPSO

    TMC will supply compressors and air-treatment equipment for the Maromba FPSO, being upgraded at COSCO Dalian for BW Energy. The vessel is intended for Brazil’s Campos basin, where first oil is targeted for late 2027.

    Source: Offshore Energy (Navingo) · Project: Maromba FPSO

3. Your weekly digest

A preview, built from what is in the Radar now. The weekly digest carries only items added since the last one; with nothing new, no digest is sent.

Pick at least one follow; the digest preview appears here.

4. Get it by e-mail

We mail a confirmation link first. No account, no password.

We store your e-mail address and what you follow - nothing else, no open or click tracking. Unsubscribing deletes both. Privacy notice.

Demand per discipline, next 18 months.

Projects and stops in a phase that needs the role group, per month, in Northwest Europe. Not people.

Northwest EuropeRest of EuropeAmericasAfricaMiddle EastAsia-Pacific

Role groupOct 2026Nov 2026Dec 2026Jan 2027Feb 2027Mar 2027Apr 2027May 2027Jun 2027Jul 2027Aug 2027Sep 2027Oct 2027Nov 2027Dec 2027Jan 2028Feb 2028Mar 2028
Project management & controls6 announced· +133 estimated5 announced· +130 estimated4 announced· +130 estimated4 announced· +130 estimated4 announced· +129 estimated4 announced· +129 estimated4 announced· +128 estimated4 announced· +126 estimated3 announced· +123 estimated3 announced· +123 estimated3 announced· +123 estimated3 announced· +120 estimated3 announced· +47 estimated3 announced· +45 estimated3 announced· +37 estimated3 announced· +36 estimated3 announced· +22 estimated3 announced· +21 estimated
Engineering & design2 announced· +94 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +93 estimated2 announced· +91 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +18 estimated2 announced· +17 estimated2 announced· +4 estimated2 announced· +4 estimated
Construction & supervision46 announced· +38 estimated38 announced· +35 estimated15 announced· +35 estimated13 announced· +35 estimated16 announced· +35 estimated23 announced· +35 estimated36 announced· +34 estimated56 announced· +33 estimated53 announced· +30 estimated46 announced· +30 estimated40 announced· +30 estimated34 announced· +30 estimated28 announced· +29 estimated13 announced· +28 estimated5 announced· +20 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +17 estimated
Commissioning & start-up3 announced· +8 estimated2 announced· +8 estimated1 announced· +8 estimated1 announced· +8 estimated1 announced· +7 estimated1 announced· +7 estimated1 announced· +7 estimated1 announced· +6 estimated+5 estimated+5 estimated+5 estimated
QA/QC & HSE5 announced· +40 estimated4 announced· +38 estimated3 announced· +38 estimated3 announced· +38 estimated3 announced· +37 estimated3 announced· +37 estimated3 announced· +36 estimated3 announced· +34 estimated2 announced· +31 estimated2 announced· +31 estimated2 announced· +31 estimated2 announced· +30 estimated2 announced· +29 estimated2 announced· +28 estimated2 announced· +20 estimated2 announced· +19 estimated2 announced· +18 estimated2 announced· +17 estimated
Document control & support3 announced· +99 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +98 estimated3 announced· +95 estimated3 announced· +95 estimated3 announced· +95 estimated3 announced· +92 estimated3 announced· +20 estimated3 announced· +19 estimated3 announced· +19 estimated3 announced· +18 estimated3 announced· +5 estimated3 announced· +5 estimated
announced: projects and stops with announced datesestimated: typical phase length, not announcedas of 2026-10-24
How we count

Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.

How the radar works.

One admission rule: an item must say where work is coming, for whom and when.

Sourced

Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is in our own words. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.

Admission

A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news is not admitted. Anything those checks cannot settle waits for a person.

Discipline matches are our inference

Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.

The same items feed The North Sea, live. To add a company, yard or area to the list: contact us.