Radar

Where work is coming.

Energy, offshore and industrial projects worldwide: when rounds are scheduled, what is being built and by whom, and where. Every date and every fact links to its source. Free to read, no sign-up.

1. Pick what you follow

What is happening around your project, your competitors and the yards you depend on.

Projects to watch
Companies & agencies
Yards
Areas
Sectors
Disciplines matched by our inference
Clear all

Latest

Awards, delays, new projects, tenders and permits — each with its date and its source. Follow something above to narrow it.

2. Your feed

  1. Milestone1 October 2026

    Hinkley Point B handed from EDF to NDA for decommissioning

    Hinkley Point B in Somerset transferred from EDF to the Nuclear Decommissioning Authority on 1 October 2026 after defuelling, with NDA subsidiary Nuclear Restoration Services taking over decommissioning. It is the second AGR site moved after Hunterston B.

    Source: UK gov.uk - Dept. for Energy Security & Net Zero

    Energy & power / grids

  2. Permit25 September 2026

    Marinus Link offshore interconnector granted final approval

    Marinus Link electricity and telecommunications interconnector in Australia secured the country's first offshore transmission license, final Commonwealth approval before construction.

    Source: Offshore Energy (Navingo)

    Energy & power / grids

  3. Award24 September 2026

    ABL appointed for marine warranty survey on Ostwind 4 grid link

    ABL secured a marine warranty survey contract from 50Hertz for the Ostwind 4 offshore grid connection project in Germany.

    Source: offshoreWIND.biz

    Energy & power / grids

  4. Milestone23 September 2026

    Nexans begins underground cable installation for Orkney Link

    Nexans has started installing the underground land cable for Orkney Link, an electricity interconnector connecting Orkney Islands to UK mainland, developed by SSEN Transmission.

    Source: Offshore Energy (Navingo)

    Energy & power / grids

  5. New project21 September 2026

    RWE commits to 400 MW battery at Moerdijk for OranjeWind wind farm

    offshoreWIND.biz reported on 21 September 2026 that RWE took final investment decision on a 400 MW/1,100 MWh battery storage system at Moerdijk, the Netherlands, to support its 795 MW OranjeWind (Hollandse Kust West VII) offshore wind farm developed with TotalEnergies, with commissioning planned for Q2 2028.

    Source: offshoreWIND.biz

    Energy & power / grids

  6. Award18 September 2026

    NSORe joint venture lands second 2 GW converter platform deal with 50Hertz

    offshoreWIND.biz reported on 18 September 2026 that the Neptun Werft-Smulders joint venture NSORe secured a second 2 GW offshore converter platform contract from German TSO 50Hertz for the LanWin3 grid connection, worth about EUR 2.5 billion combined with the earlier LanWin6 award.

    Source: offshoreWIND.biz

    Energy & power / grids

Show older items
  1. New projectSource checked 18 September 2026

    TenneT 2GW programme: 14 offshore grid connections by about 2032

    Seven Dutch and seven German 2GW HVDC connections on one standard design. Nederwiek 1 and 2 are targeted for 2030, Doordewind 1 and 2 land at Eemshaven.

    Source: TenneT

    Energy & power / grids

  2. MilestoneSource checked 18 September 2026

    Heerema begins building the jacket for IJmuiden Ver Gamma

    Heerema Fabrication Group has started construction of the jacket for TenneT's IJmuiden Ver Gamma platform in Vlissingen; the Nederwiek 2 jacket follows at the same yard. Each jacket weighs roughly 10,000 tonnes.

    Source: reNEWS

    Energy & power / grids

  3. MilestoneSource checked 18 September 2026

    TenneT completes its 700 MW offshore programme with Hollandse Kust (west Beta)

    The Hollandse Kust (west Beta) substation received its grid-readiness certificate ahead of schedule, closing TenneT's series of 700 MW AC connections.

    Source: TenneT

    Energy & power / grids

  4. Permit14 September 2026

    UK planning body approves grid links for Morecambe and Morgan wind farms

    offshoreWIND.biz reported that the UK Planning Inspectorate approved a Development Consent Order on 14 September 2026 for shared transmission infrastructure serving the 480 MW Morecambe and 1.5 GW Morgan offshore wind farms.

    Source: offshoreWIND.biz

    Energy & power / grids

  5. Milestone31 August 2026

    Jacket for TenneT's IJmuiden Ver Beta platform takes shape in Vlissingen

    The jacket for the IJmuiden Ver Beta 2GW platform is being assembled at Heerema's Vlissingen yard. TenneT targets commissioning of the connection in 2028.

    Source: offshoreWIND.biz

    Energy & power / grids

  6. Award3 August 2026

    Larsen & Toubro and Hitachi Energy sign 2GW framework agreement with TenneT

    The consortium continues IJmuiden Ver Alpha and Nederwiek 1 and starts two new 2GW systems, Nederwiek 3 and LanWin 5 (Germany). L&T takes the offshore converter platforms, Hitachi Energy the HVDC technology. No contract value was published.

    Source: Evertiq

    Energy & power / grids

  7. Award9 July 2026

    SSEN Transmission picks Van Oord-Sumitomo group for HVDC framework works

    Van Oord reported that a Van Oord-Sumitomo consortium signed a long-term framework agreement with SSEN Transmission covering HVDC-related works.

    Source: Van Oord

    Energy & power / grids

  8. Delay20 February 2026

    Hinkley Point C cost climbs to £35bn as Unit 1 start-up confirmed for 2030

    EDF's 2025 results, reported 20 February 2026, raised Hinkley Point C's cost estimate to £35bn (2015 prices) and confirmed Unit 1 will not start generating until 2030, citing lower productivity in electromechanical installation work.

    Source: The Energy Tribune

    Energy & power / grids

  9. Delay25 April 2024

    Dutch 21 GW offshore wind target moved to the end of 2032

    In a letter to parliament of 25 April 2024 the minister moved the 21 GW milestone from around 2030 to the end of 2032, citing tender sequencing, grid connection capacity and the supply chain.

    Source: Noordzeeloket

    Energy & power / grids

  10. Award17 May 2023

    TenneT awards 2GW platform transport and installation to Heerema and Allseas

    Multi-year framework agreements cover transport and installation of the 2GW offshore converter platforms, with installation slots running to 2031.

    Source: TenneT

    Energy & power / grids

3. Your weekly digest

Built from what is in the radar now. A real digest only carries what is new since the last one — and is skipped when there is nothing.

YRproject  Radar  ·  Week of 12 October 2026
This is what your weekly digest would look like
Following: Energy & power / grids
Awards & contracts
24 September 2026
ABL secured a marine warranty survey contract from 50Hertz for the Ostwind 4 offshore grid connection project in Germany.
Source: offshoreWIND.biz
You follow Energy & power / grids
18 September 2026
offshoreWIND.biz reported on 18 September 2026 that the Neptun Werft-Smulders joint venture NSORe secured a second 2 GW offshore converter platform contract from German TSO 50Hertz for the LanWin3 grid connection, worth about EUR 2.5 billion combined with the earlier LanWin6 award.
Source: offshoreWIND.biz
You follow Energy & power / grids
Permits
25 September 2026
Marinus Link electricity and telecommunications interconnector in Australia secured the country's first offshore transmission license, final Commonwealth approval before construction.
Source: Offshore Energy (Navingo)
You follow Energy & power / grids
New projects
21 September 2026
offshoreWIND.biz reported on 21 September 2026 that RWE took final investment decision on a 400 MW/1,100 MWh battery storage system at Moerdijk, the Netherlands, to support its 795 MW OranjeWind (Hollandse Kust West VII) offshore wind farm developed with TotalEnergies, with commissioning planned for Q2 2028.
Source: offshoreWIND.biz
You follow Energy & power / grids
Milestones
1 October 2026
Hinkley Point B in Somerset transferred from EDF to the Nuclear Decommissioning Authority on 1 October 2026 after defuelling, with NDA subsidiary Nuclear Restoration Services taking over decommissioning. It is the second AGR site moved after Hunterston B.
Source: UK gov.uk - Dept. for Energy Security & Net Zero
You follow Energy & power / grids
23 September 2026
Nexans has started installing the underground land cable for Orkney Link, an electricity interconnector connecting Orkney Islands to UK mainland, developed by SSEN Transmission.
Source: Offshore Energy (Navingo)
You follow Energy & power / grids
This week on the calendar
12 Oct 2026 · window closes
Summaries are our own words; the linked source is what counts. We do not track opens or clicks.
YRproject is open book: the professional keeps the full rate; our fee comes on top, 20% to 500 hours, 15% to 1,500 and 12% above - and both sides see the same invoice. See who gets what
Every digest ends with a manage link and a one-step unsubscribe
YRproject B.V., the Netherlands. KvK 97813974

4. Get it by e-mail

We mail a confirmation link first. No account, no password.

We store your e-mail address and what you follow - nothing else, no open or click tracking. Unsubscribing deletes both. Privacy notice.

How the radar works.

No scraped walls of news. Short, sourced, dated — and admitted only against a fixed rule.

Sourced

Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is our own words; the source is what counts. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.

Admitted, not scraped

A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news never qualifies. Anything those checks cannot settle waits for a person, and we remove what should not be here.

Inference, labelled

Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.

The same items feed The North Sea, live. Missing a company, yard or area? Tell us and we add it to the list.