Project · Offshore wind · Poland
Bałtyk 2 & Bałtyk 3 offshore wind
Poland's largest sanctioned offshore wind build (PLN ~27 bn) is mid-installation: substation topsides, cables and 100 turbines still go in during 2026–2027.
Checked by hand against the sources below (2026-10-20).
- Engineering (done)
- Fabrication (done)
- Transport & installation (now)
- Hook-up
- Commissioning (next)
- Operation
Now Transport & installation (reported: installation (all 100 foundations and 2 substation jackets in place by August 2026; export cables being installed and brought ashore;…)
Next Commissioning · 2027 (first power 2027, as reported)
Roles Commissioning & start-up · QA/QC & HSE · Project management & controls · Role groups per phase: our planning assumption from the Crew Forecast model.
Later Operation 2028 (full commercial operation 2028, as reported)
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- EquinorOperator / ownerco-developer/owner
- PolenergiaOperator / ownerco-developer/owner
- Heerema Marine ContractorsTransport & installationtransport and installation of 100 monopiles, 100 transition pieces and two offshore substation jackets (SSCV Thialf; campaign completed Sept 2026); returns to…
- Siemens GamesaEquipment & supplyturbine supplier — 100 x 14.4 MW (per offshoreWIND.biz)
- Sif GroupEquipment & supplymonopiles and transition pieces supply (per offshoreWIND.biz)
- SmuldersEquipment & supplymonopiles and transition pieces supply (per offshoreWIND.biz)
- IemantsEngineering & designdesign and construction of the offshore substations (per offshoreWIND.biz)
- Kind
- Offshore wind
- Country
- Poland
- Size
- 2 x 720 MW; 100 monopile foundations; first power 2027, COD 2028
- Operator
- Equinor
- Position
- 54.85°N 17.00°E, approximate
On the Radar each linked to its source
Sources
- All Foundations In Place at Bałtyk 2 & 3offshoreWIND.biz · published 2026-09-03 · read 2026-09-22
- Equinor and Polenergia with contracts for transportation and installation of offshore wind farm foundations for Bałtyk 2 and 3Polenergia (company newsroom) · published 2024-07-03 · read 2026-09-22
- Equinor and Polenergia take Final Investment Decisions (FIDs) for Bałtyk 2 and Bałtyk 3 offshore wind projectsPolenergia (company newsroom) · published 2025-05-19 · read 2026-09-22
- Progress of workBałtyk 2 & 3 project site (Equinor/Polenergia) · published 2026-08 · read 2026-10-20
- First projects submitted. Applications for Equinor and Polenergia contest open until 23 OctoberEquinor / Polenergia · published 2026-10-14 · read 2026-10-20
- Polenergia notuje zyski za półrocze, zbliżając się do nowych mocyPolenergia · published 2026-10-01 · read 2026-10-20