Project · Offshore wind · Poland

Bałtyk 2 & Bałtyk 3 offshore wind

Poland's largest sanctioned offshore wind build (PLN ~27 bn) is mid-installation: substation topsides, cables and 100 turbines still go in during 2026–2027.

Checked by hand against the sources below (2026-10-20).

  1. Engineering (done)
  2. Fabrication (done)
  3. Transport & installation (now)
  4. Hook-up
  5. Commissioning (next)
  6. Operation

Now Transport & installation (reported: installation (all 100 foundations and 2 substation jackets in place by August 2026; export cables being installed and brought ashore;…)

Next Commissioning · 2027 (first power 2027, as reported)

Roles Commissioning & start-up · QA/QC & HSE · Project management & controls · Role groups per phase: our planning assumption from the Crew Forecast model.

Later Operation 2028 (full commercial operation 2028, as reported)

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • EquinorOperator / ownerco-developer/owner
  • PolenergiaOperator / ownerco-developer/owner
  • Heerema Marine ContractorsTransport & installationtransport and installation of 100 monopiles, 100 transition pieces and two offshore substation jackets (SSCV Thialf; campaign completed Sept 2026); returns to…
  • Siemens GamesaEquipment & supplyturbine supplier — 100 x 14.4 MW (per offshoreWIND.biz)
  • Sif GroupEquipment & supplymonopiles and transition pieces supply (per offshoreWIND.biz)
  • SmuldersEquipment & supplymonopiles and transition pieces supply (per offshoreWIND.biz)
  • IemantsEngineering & designdesign and construction of the offshore substations (per offshoreWIND.biz)
Kind
Offshore wind
Country
Poland
Size
2 x 720 MW; 100 monopile foundations; first power 2027, COD 2028
Operator
Equinor
Position
54.85°N 17.00°E, approximate

Sources

  1. All Foundations In Place at Bałtyk 2 & 3offshoreWIND.biz · published 2026-09-03 · read 2026-09-22
  2. Equinor and Polenergia with contracts for transportation and installation of offshore wind farm foundations for Bałtyk 2 and 3Polenergia (company newsroom) · published 2024-07-03 · read 2026-09-22
  3. Equinor and Polenergia take Final Investment Decisions (FIDs) for Bałtyk 2 and Bałtyk 3 offshore wind projectsPolenergia (company newsroom) · published 2025-05-19 · read 2026-09-22
  4. Progress of workBałtyk 2 & 3 project site (Equinor/Polenergia) · published 2026-08 · read 2026-10-20
  5. First projects submitted. Applications for Equinor and Polenergia contest open until 23 OctoberEquinor / Polenergia · published 2026-10-14 · read 2026-10-20
  6. Polenergia notuje zyski za półrocze, zbliżając się do nowych mocyPolenergia · published 2026-10-01 · read 2026-10-20