Planned stops at power stations
167 stops of 14 days or more in 12 countries over the next 12 months, plus 5 deratings. Most megawatts stand still in the week of 31 May 2027.
Megawatts standing still, per week
Source: Elexon Insights, REMIT, Elia open data, ods202, Nord Pool UMM · 24 Oct 2026
A stop needs commissioning, I&C and turbine people.
Work announced at sea
183 notices to mariners on 107 wind farms, fields and sea areas, October 2026 to March 2027.
Notice-weeks per month
Source: Danish Maritime Authority, Niord notices to mariners, Kingfisher Information Service · 24 Oct 2026
Crew for one of these campaigns?
Installation vessels, week of 5 to 11 Oct 2026
Daily positions of 65 of the 96 crane, cable, pipelay and jack-up vessels in the register. Satellite AIS runs ten days behind; this is a closed week, not live.
lying stillunder way
Source: Kystverket, Kystdatahuset (AIS) · 24 Oct 2026
Helicopter passengers per base
Offshore helicopter passengers per month in Norway and the UK. On 23 Oct, 75 departures were planned from the six Norwegian bases; 65 flew.
- Aberdeen23,618
- Stavanger17,228
- Bergen14,215
- Kristiansund5,964
- Norwich5,158
- Sumburgh4,704
- Florø2,175
- Brønnøysund2,588
- Blackpool2,102
- Hammerfest1,330
- Humberside925
Sep 2024Aug 2026
Passengers per month · figure: Aug 2026
Source: Statistics Norway (SSB), table 08507, UK Civil Aviation Authority, airport data table 19, Flight data from Avinor · 24 Oct 2026
Workable days at sea
K13a wave buoy, Dutch North Sea, October 2026: 8 of 23 measured days with waves of 1.5 m or less from 07:00 to 19:00.
workablenotto come
Source: Rijkswaterstaat Waterwebservices, measured · 23 Oct 2026
Below: the latest items, what you follow and the weekly digest. Or ask a question and get the answer with its sources.
When are you needed? Your discipline and your date: the projects that start then
Latest
Awards, delays, new projects, tenders and permits, newest first. Follow something above to narrow the list.
2. Your feed
FSO achieves first oil ahead of schedule offshore Vietnam
Yinson Production and PTSC reached first oil at an FSO vessel deployed offshore Vietnam ahead of schedule.
Source: Offshore Energy (Navingo)
Offshore
DOF secures subsea installation contract in Africa for 2027
DOF Group won a subsea installation contract in Africa for 100 days of vessel work in early 2027.
Source: Offshore Energy (Navingo)
Offshore
Infill drilling underway offshore Oman, production targeted for November 2026
Masirah Oil has commenced infill well drilling at an offshore Oman oil field with production expected by November 2026.
Source: Offshore Energy (Navingo)
Offshore
Técnicas Reunidas wins LNG Canada Coastal GasLink Phase 2 EPCM contract
Técnicas Reunidas awarded €200M+ EPCM contract for LNG Canada's Coastal GasLink Phase 2 project.
Source: Offshore Energy (Navingo) · Project: Coastal GasLink Phase 2
Offshore
Wood Thilsted awarded design contract for Outer Dowsing monopiles
Wood Thilsted secured a contract for detailed design of up to 100 monopile foundations for the 1.5 GW Outer Dowsing offshore wind farm.
Source: offshoreWIND.biz · Project: Outer Dowsing offshore wind farm
Offshore
Transocean drillships secure $550M US Gulf contracts
Transocean awarded multi-well ultra-deepwater contracts for two drillships in the U.S. Gulf extending through 2027.
Source: Offshore Energy (Navingo)
Offshore
Show older items
Prospector 5 mobilises for four-well MaBoMo production campaign off Gabon
Borr Prospector 5 is mobilising to the MaBoMo platform for BW Energy’s Dussafu development off Gabon. The planned Phase 2 campaign covers four production infill wells at Hibiscus and Hibiscus South, with the first new well expected on stream in early 2027.
Source: Offshore Energy (Navingo)
Offshore
Mari Energies awards EMGS offshore survey work in Pakistan
EMGS received a letter of award from Mari Energies for electromagnetic data acquisition across offshore exploration blocks in Pakistan. The 16 October report gives no mobilisation date or contract value.
Source: Offshore Energy (Navingo)
Offshore
TMC wins air-system package for Brazil-bound Maromba FPSO
TMC will supply compressors and air-treatment equipment for the Maromba FPSO, being upgraded at COSCO Dalian for BW Energy. The vessel is intended for Brazil’s Campos basin, where first oil is targeted for late 2027.
Source: Offshore Energy (Navingo) · Project: Maromba FPSO
Offshore
France’s 10 GW AO10 offshore-wind bid window has closed
France’s AO10 bid deadline passed at noon on 12 October. CRE will assess offers for eleven fixed and floating offshore-wind projects, with awards planned for February 2027; bidder names have not been disclosed.
Source: offshoreWIND.biz
Offshore
Finder selects ENEOS rig for Timor-Leste wells, subject to approvals
Finder’s conditional ENEOS award covers three KTJ development wells off Timor-Leste, with two options. Drilling is scheduled from 1 December 2027 for about 150 days; board and government approvals remain outstanding.
Source: Offshore Energy (Navingo) · Project: KTJ
Offshore
Worley awarded subsea structures contract for Northern Lights Phase 2
Subsea7 contracted Worley Rosenberg to fabricate key subsea structures and spools for Northern Lights' second phase.
Source: Offshore Energy (Navingo) · Project: Northern Lights CO2 transport & storage — Phase 2
Offshore
DEME awarded turbine transport and installation contract for Dutch offshore wind
Vattenfall and Copenhagen Infrastructure Partners awarded DEME a contract to transport and install 69 wind turbines at the first phase of their 1 GW Dutch offshore wind farm.
Source: offshoreWIND.biz
Offshore
Worley Rosenberg awarded subsea fabrication for Northern Lights Phase 2
Worley Rosenberg has been awarded a fabrication scope from Subsea7 for subsea infrastructure supporting Phase II of Norway's Northern Lights CCS development.
Source: Worley - news · Project: Northern Lights CO2 transport & storage — Phase 2
Offshore
Sunda secures exclusive New Zealand gas field exploration permit bid
Sunda has secured exclusivity for a New Zealand exploration permit bid for a gas field appraisal.
Source: Offshore Energy (Navingo)
Offshore
DOF secures one-year extension for Skandi Nomad CSV
Norway's DOF Group extended a contract for construction support vessel Skandi Nomad for one year starting October 2025.
Source: Offshore Energy (Navingo)
Offshore
Saab wins Ørsted subsea-inspection vehicle order
Ørsted ordered another Seaeye Cougar ROV from Saab UK for inspection and maintenance of offshore-wind foundations and cables. The order reported on 13 October expands its Cougar fleet to three; delivery timing was not stated.
Source: offshoreWIND.biz
Offshore
Murphy reports first oil at Vietnam’s Lac Da Vang and a US Gulf well
Murphy reported first oil at Lac Da Vang off Vietnam on 27 September and production from Chinook #8 in the US Gulf. The 13 October update says additional Vietnamese development wells will be brought online through 2028.
Source: Offshore Energy (Navingo)
Offshore
Cadeler orders East Anglia Two lifting equipment from Hampidjan Advant
Hampidjan Advant will manufacture lifting slings for Cadeler’s East Anglia Two installation campaign off England. Offshore work is scheduled for 2027; the agreement supports handling foundations and turbines.
Source: offshoreWIND.biz · Project: East Anglia 2 offshore wind farm
Offshore
TotalEnergies awards Vallourec tubular contract for Azerbaijan gas
TotalEnergies contracted Vallourec to supply over 16,000 tons of tubular products for a gas field development.
Source: Offshore Energy (Navingo)
Offshore
3. Your weekly digest
A preview, built from what is in the Radar now. The weekly digest carries only items added since the last one; with nothing new, no digest is sent.
|
4. Get it by e-mail
Demand per discipline, next 18 months.
Projects and stops in a phase that needs the role group, per month, in Northwest Europe. Not people.
Northwest EuropeRest of EuropeAmericasAfricaMiddle EastAsia-Pacific
| Role group | Oct 2026 | Nov 2026 | Dec 2026 | Jan 2027 | Feb 2027 | Mar 2027 | Apr 2027 | May 2027 | Jun 2027 | Jul 2027 | Aug 2027 | Sep 2027 | Oct 2027 | Nov 2027 | Dec 2027 | Jan 2028 | Feb 2028 | Mar 2028 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Project management & controls | 6 announced· +133 estimated | 5 announced· +130 estimated | 4 announced· +130 estimated | 4 announced· +130 estimated | 4 announced· +129 estimated | 4 announced· +129 estimated | 4 announced· +128 estimated | 4 announced· +126 estimated | 3 announced· +123 estimated | 3 announced· +123 estimated | 3 announced· +123 estimated | 3 announced· +120 estimated | 3 announced· +47 estimated | 3 announced· +45 estimated | 3 announced· +37 estimated | 3 announced· +36 estimated | 3 announced· +22 estimated | 3 announced· +21 estimated |
| Engineering & design | 2 announced· +94 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +93 estimated | 2 announced· +91 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +18 estimated | 2 announced· +17 estimated | 2 announced· +4 estimated | 2 announced· +4 estimated |
| Construction & supervision | 46 announced· +38 estimated | 38 announced· +35 estimated | 15 announced· +35 estimated | 13 announced· +35 estimated | 16 announced· +35 estimated | 23 announced· +35 estimated | 36 announced· +34 estimated | 56 announced· +33 estimated | 53 announced· +30 estimated | 46 announced· +30 estimated | 40 announced· +30 estimated | 34 announced· +30 estimated | 28 announced· +29 estimated | 13 announced· +28 estimated | 5 announced· +20 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +17 estimated |
| Commissioning & start-up | 3 announced· +8 estimated | 2 announced· +8 estimated | 1 announced· +8 estimated | 1 announced· +8 estimated | 1 announced· +7 estimated | 1 announced· +7 estimated | 1 announced· +7 estimated | 1 announced· +6 estimated | +5 estimated | +5 estimated | +5 estimated | |||||||
| QA/QC & HSE | 5 announced· +40 estimated | 4 announced· +38 estimated | 3 announced· +38 estimated | 3 announced· +38 estimated | 3 announced· +37 estimated | 3 announced· +37 estimated | 3 announced· +36 estimated | 3 announced· +34 estimated | 2 announced· +31 estimated | 2 announced· +31 estimated | 2 announced· +31 estimated | 2 announced· +30 estimated | 2 announced· +29 estimated | 2 announced· +28 estimated | 2 announced· +20 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +17 estimated |
| Document control & support | 3 announced· +99 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +98 estimated | 3 announced· +95 estimated | 3 announced· +95 estimated | 3 announced· +95 estimated | 3 announced· +92 estimated | 3 announced· +20 estimated | 3 announced· +19 estimated | 3 announced· +19 estimated | 3 announced· +18 estimated | 3 announced· +5 estimated | 3 announced· +5 estimated |
How we count
Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.
How the radar works.
One admission rule: an item must say where work is coming, for whom and when.
Sourced
Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is in our own words. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.
Admission
A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news is not admitted. Anything those checks cannot settle waits for a person.
Discipline matches are our inference
Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.
The same items feed The North Sea, live. To add a company, yard or area to the list: contact us.