Radar

Where work is coming.

Energy, offshore and industrial projects worldwide: when rounds are scheduled, what is being built and by whom, and where. Every date and every fact links to its source. Free to read, no sign-up.

1. Pick what you follow

What is happening around your project, your competitors and the yards you depend on.

Projects to watch
Companies & agencies
Yards
Areas
Sectors
Disciplines matched by our inference
Clear all

Latest

Awards, delays, new projects, tenders and permits — each with its date and its source. Follow something above to narrow it.

2. Your feed

  1. New projectSource checked 18 September 2026

    TenneT 2GW programme: 14 offshore grid connections by about 2032

    Seven Dutch and seven German 2GW HVDC connections on one standard design. Nederwiek 1 and 2 are targeted for 2030, Doordewind 1 and 2 land at Eemshaven.

    Source: TenneT

    Nederwiek

  2. MilestoneSource checked 18 September 2026

    Heerema begins building the jacket for IJmuiden Ver Gamma

    Heerema Fabrication Group has started construction of the jacket for TenneT's IJmuiden Ver Gamma platform in Vlissingen; the Nederwiek 2 jacket follows at the same yard. Each jacket weighs roughly 10,000 tonnes.

    Source: reNEWS

    Nederwiek

  3. Award3 August 2026

    Larsen & Toubro and Hitachi Energy sign 2GW framework agreement with TenneT

    The consortium continues IJmuiden Ver Alpha and Nederwiek 1 and starts two new 2GW systems, Nederwiek 3 and LanWin 5 (Germany). L&T takes the offshore converter platforms, Hitachi Energy the HVDC technology. No contract value was published.

    Source: Evertiq

    Nederwiek

  4. Tender31 October 2025

    No bids for the Nederwiek I-A site; no re-tender followed

    RVO received no applications for the 1 GW Nederwiek I-A site by the 30 October 2025 deadline. No re-tender of Nederwiek I-A has taken place; the subsidised 2026 round the government prepared went instead to IJmuiden Ver Gamma-A and Gamma-B (application window 26 November-10 December 2026).

    Source: Windpower NL / RVO

    Nederwiek

  5. Delay25 April 2024

    Dutch 21 GW offshore wind target moved to the end of 2032

    In a letter to parliament of 25 April 2024 the minister moved the 21 GW milestone from around 2030 to the end of 2032, citing tender sequencing, grid connection capacity and the supply chain.

    Source: Noordzeeloket

    Nederwiek

3. Your weekly digest

Built from what is in the radar now. A real digest only carries what is new since the last one — and is skipped when there is nothing.

YRproject  Radar  ·  Week of 12 October 2026
This is what your weekly digest would look like
Following: Nederwiek
Awards & contracts
3 August 2026
The consortium continues IJmuiden Ver Alpha and Nederwiek 1 and starts two new 2GW systems, Nederwiek 3 and LanWin 5 (Germany). L&T takes the offshore converter platforms, Hitachi Energy the HVDC technology. No contract value was published.
Source: Evertiq
You follow Nederwiek
Tenders
31 October 2025
RVO received no applications for the 1 GW Nederwiek I-A site by the 30 October 2025 deadline. No re-tender of Nederwiek I-A has taken place; the subsidised 2026 round the government prepared went instead to IJmuiden Ver Gamma-A and Gamma-B (application window 26 November-10 December 2026).
Source: Windpower NL / RVO
You follow Nederwiek
Delays & schedule changes
25 April 2024
In a letter to parliament of 25 April 2024 the minister moved the 21 GW milestone from around 2030 to the end of 2032, citing tender sequencing, grid connection capacity and the supply chain.
Source: Noordzeeloket
You follow Nederwiek
New projects
Source checked 18 September 2026
Seven Dutch and seven German 2GW HVDC connections on one standard design. Nederwiek 1 and 2 are targeted for 2030, Doordewind 1 and 2 land at Eemshaven.
Source: TenneT
You follow Nederwiek
Milestones
Source checked 18 September 2026
Heerema Fabrication Group has started construction of the jacket for TenneT's IJmuiden Ver Gamma platform in Vlissingen; the Nederwiek 2 jacket follows at the same yard. Each jacket weighs roughly 10,000 tonnes.
Source: reNEWS
You follow Nederwiek
This week on the calendar
12 Oct 2026 · window closes
Summaries are our own words; the linked source is what counts. We do not track opens or clicks.
YRproject is open book: the professional keeps the full rate; our fee comes on top, 20% to 500 hours, 15% to 1,500 and 12% above - and both sides see the same invoice. See who gets what
Every digest ends with a manage link and a one-step unsubscribe
YRproject B.V., the Netherlands. KvK 97813974

4. Get it by e-mail

We mail a confirmation link first. No account, no password.

We store your e-mail address and what you follow - nothing else, no open or click tracking. Unsubscribing deletes both. Privacy notice.

How the radar works.

No scraped walls of news. Short, sourced, dated — and admitted only against a fixed rule.

Sourced

Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is our own words; the source is what counts. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.

Admitted, not scraped

A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news never qualifies. Anything those checks cannot settle waits for a person, and we remove what should not be here.

Inference, labelled

Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.

The same items feed The North Sea, live. Missing a company, yard or area? Tell us and we add it to the list.