TenneT 2GW programme: 14 offshore grid connections by about 2032
Seven Dutch and seven German 2GW HVDC connections on one standard design. Nederwiek 1 and 2 are targeted for 2030, Doordewind 1 and 2 land at Eemshaven.
Source: TenneT
IJmuiden Ver
IJmuiden Ver Gamma-A and Gamma-B: permit decisions expected early 2027
RVO runs the 2026 round for two sites of about 1 GW each, with a subsidy ceiling per site. Permit and subsidy decisions are planned for the first quarter of 2027; the wind farms are expected to produce from 2032.
Source: RVO
IJmuiden Ver
Heerema begins building the jacket for IJmuiden Ver Gamma
Heerema Fabrication Group has started construction of the jacket for TenneT's IJmuiden Ver Gamma platform in Vlissingen; the Nederwiek 2 jacket follows at the same yard. Each jacket weighs roughly 10,000 tonnes.
Source: reNEWS
IJmuiden Ver
Jacket for TenneT's IJmuiden Ver Beta platform takes shape in Vlissingen
The jacket for the IJmuiden Ver Beta 2GW platform is being assembled at Heerema's Vlissingen yard. TenneT targets commissioning of the connection in 2028.
Source: offshoreWIND.biz
IJmuiden Ver
Larsen & Toubro and Hitachi Energy sign 2GW framework agreement with TenneT
The consortium continues IJmuiden Ver Alpha and Nederwiek 1 and starts two new 2GW systems, Nederwiek 3 and LanWin 5 (Germany). L&T takes the offshore converter platforms, Hitachi Energy the HVDC technology. No contract value was published.
Source: Evertiq
IJmuiden Ver
Dutch government adds a second site to the 2026 tender round
The Dutch government added IJmuiden Ver Gamma-B, with subsidy, to the 2026 tender round next to Gamma-A. Each site is roughly 1 GW.
Source: offshoreWIND.biz
IJmuiden Ver
Show older items
IJmuiden Ver Alpha and Beta permits awarded
Noordzeker (SSE Renewables, ABP, AGP) won the Alpha site and Zeevonk II (Vattenfall and Copenhagen Infrastructure Partners) the Beta site. TenneT's grid connections for both are targeted for 2028-2029.
Source: Vattenfall
IJmuiden Ver
Dutch 21 GW offshore wind target moved to the end of 2032
In a letter to parliament of 25 April 2024 the minister moved the 21 GW milestone from around 2030 to the end of 2032, citing tender sequencing, grid connection capacity and the supply chain.
Source: Noordzeeloket
IJmuiden Ver
3. Your weekly digest
Built from what is in the radar now. A real digest only carries what is new since the last one — and is skipped when there is nothing.
|
4. Get it by e-mail
How the radar works.
No scraped walls of news. Short, sourced, dated — and admitted only against a fixed rule.
Sourced
Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is our own words; the source is what counts. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.
Admitted, not scraped
A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news never qualifies. Anything those checks cannot settle waits for a person, and we remove what should not be here.
Inference, labelled
Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.
The same items feed The North Sea, live. Missing a company, yard or area? Tell us and we add it to the list.