YRproject Radar
Awards, tenders, start-ups and delays, worldwide.
Offshore wind, grid, oil and gas, LNG, hydrogen and CCS projects. Each item carries its date and links to its source. Free to read, no sign-up.
Where work is coming.
Planned stops at power stations
166 stops of 14 days or more in 12 countries over the next 12 months, plus 6 deratings. Most megawatts stand still in the week of 31 May 2027.
Megawatts standing still, per week
Source: Elexon Insights, REMIT, Elia open data, ods202, Nord Pool UMM · 3 Nov 2026
A stop needs commissioning, I&C and turbine people.
Work announced at sea
169 notices to mariners on 101 wind farms, fields and sea areas, November 2026 to April 2027.
Notice-weeks per month
Source: Danish Maritime Authority, Niord notices to mariners, Kingfisher Information Service · 3 Nov 2026
Crew for one of these campaigns?
Installation vessels, week of 5 to 11 Oct 2026
Daily positions of 65 of the 96 crane, cable, pipelay and jack-up vessels in the register. Satellite AIS runs ten days behind; this is a closed week, not live.
lying stillunder way
Source: Kystverket, Kystdatahuset (AIS) · 27 Oct 2026
Helicopter passengers per base
Offshore helicopter passengers per month in Norway and the UK. On 2 Nov, 95 departures were planned from the six Norwegian bases; 71 flew.
- Aberdeen23,618
- Stavanger20,067
- Bergen14,138
- Kristiansund6,684
- Norwich5,158
- Sumburgh4,704
- Florø2,418
- Brønnøysund2,088
- Blackpool2,102
- Hammerfest1,494
- Humberside925
Sep 2024Aug 2026
Passengers per month · figure: Aug 2026
Source: Statistics Norway (SSB), table 08507, UK Civil Aviation Authority, airport data table 19, Flight data from Avinor · 3 Nov 2026
Workable days at sea
K13a wave buoy, Dutch North Sea, November 2026: 1 of 2 measured days with waves of 1.5 m or less from 07:00 to 19:00.
workablenotto come
Source: Rijkswaterstaat Waterwebservices, measured · 2 Nov 2026
Below: the latest items, what you follow and the weekly digest. Or ask a question and get the answer with its sources.
When are you needed? Your discipline and your date: the projects that start then
Latest
Awards, delays, new projects, tenders and permits, newest first. Follow something above to narrow the list.
2. Your feed
Final turbine installed at Ecowende 760 MW offshore wind farm
Van Oord and Vestas completed installation of the final turbine at the 760 MW Ecowende offshore wind farm in the Dutch North Sea.
Source: offshoreWIND.biz
Search: instal
Wind turbine installation begins at Inch Cape offshore Scotland
Installation of Vestas V236-15.0 MW wind turbines has started at Inch Cape offshore Scotland using Cadeler's installation vessel.
Source: offshoreWIND.biz
Search: instal
Ecowende offshore wind farm completes turbine installation
The 52nd and final wind turbine at Ecowende offshore wind farm was installed on October 30th 2026 in the Hollandse Kust (west) zone, with the project entering its final construction phase.
Source: Van Oord - news
Search: instal
44 turbines installed at Coastal Virginia offshore wind farm
One quarter of 176 turbines have been installed at the Coastal Virginia Offshore Wind site.
Source: offshoreWIND.biz · Project: Coastal Virginia Offshore Wind (CVOW)
Search: instal
Two offshore platforms installed at Egypt's North Sinai gas field
Petroleum Marine Services installed two offshore platforms at North Sinai's gas field to expand Egypt's energy infrastructure.
Source: Offshore Energy (Navingo)
Search: instal
DEME and Prysmian begin cable installation for TenneT grid
DEME and Prysmian have started high-voltage cable installation for TenneT in Veerse Meer, Netherlands.
Source: offshoreWIND.biz
Search: instal
Show older items
Seaway7 completes cable installation at East Anglia Three
Seaway7 finished final inner-array cable lay at the 1.4 GW East Anglia Three offshore wind farm in the UK.
Source: offshoreWIND.biz
Search: instal
DOF secures subsea installation contract in Africa for 2027
DOF Group won a subsea installation contract in Africa for 100 days of vessel work in early 2027.
Source: Offshore Energy (Navingo)
Search: instal
Taiwan's Hai Long offshore wind farm fully operational
All 73 turbines at the 1,022 MW Hai Long offshore wind project in Taiwan are installed and generating electricity.
Source: offshoreWIND.biz
Search: instal
DEME awarded turbine transport and installation contract for Dutch offshore wind
Vattenfall and Copenhagen Infrastructure Partners awarded DEME a contract to transport and install 69 wind turbines at the first phase of their 1 GW Dutch offshore wind farm.
Source: offshoreWIND.biz
Search: instal
Cadeler orders East Anglia Two lifting equipment from Hampidjan Advant
Hampidjan Advant will manufacture lifting slings for Cadeler’s East Anglia Two installation campaign off England. Offshore work is scheduled for 2027; the agreement supports handling foundations and turbines.
Source: offshoreWIND.biz · Project: East Anglia 2 offshore wind farm
Search: instal
Inter-array cable installation begins at Hornsea 3 UK wind farm
Seaway7 to start installing inter-array cables at the 2.9 GW Hornsea 3 offshore wind farm in the UK.
Source: Offshore Energy (Navingo)
Search: instal
Valeura starts offshore installation in Gulf of Thailand ahead of schedule
Valeura Energy commenced offshore installation at its Gulf of Thailand field approximately two months ahead of schedule.
Source: Offshore Energy (Navingo)
Search: instal
World-first offshore CO2 transport and storage platform installed
Installation of what is described as the world's first offshore platform dedicated to CO2 transportation and storage for industrial decarbonization offshore UK.
Source: Offshore Energy (Navingo)
Search: instal
Dogger Bank B reaches halfway point in turbine installation
Forty-nine wind turbines installed at Dogger Bank B offshore wind farm in the UK, passing the halfway mark.
Source: offshoreWIND.biz
Search: instal
All turbines installed at Poland's Baltic Power wind farm
All 76 Vestas V236-15.0 MW turbines installed at Baltic Power offshore wind farm in Poland, jointly owned by Orlen and Northland Power.
Source: offshoreWIND.biz · Project: Bałtyk 2 & Bałtyk 3 offshore wind
Search: instal
Subsea Micropiles to handle anchor design and site surveys for Pentland floating wind
Subsea Micropiles signed an agreement to deliver site investigations and anchor engineering, including installation support, for the 100 MW Pentland floating wind farm led by Highland Wind Limited. FID is expected in 2027 and operation in 2030.
Source: offshoreWIND.biz · Project: Pentland floating wind farm
Search: instal
Final monopile installed at Nordlicht I offshore wind farm
DEME completed installation of the 68th and final monopile at Vattenfall's Nordlicht I offshore wind farm in the German North Sea.
Source: offshoreWIND.biz
Search: instal
Boskalis wins inter-array cable contract for Dutch offshore wind
Boskalis secured a contract to transport and install inter-array cables for the first phase of a 2 GW Dutch offshore wind farm.
Source: Offshore Energy (Navingo)
Search: instal
Neptun Deep in final execution, first gas targeted for first half of 2027
OMV Petrom and Romgaz have installed the Neptun Alpha platform and finished seven of ten wells at Neptun Deep in the Romanian Black Sea. First gas is targeted for H1 2027, with subsea work and pipeline tie-in still to come.
Source: Offshore Energy (Navingo)
Search: instal
3. Your weekly digest
A preview, built from what is in the Radar now. The weekly digest carries only items added since the last one; with nothing new, no digest is sent.
|
4. Get it by e-mail
Demand per discipline, next 18 months.
Projects and stops in a phase that needs the role group, per month, in Northwest Europe. Not people.
Northwest EuropeRest of EuropeAmericasAfricaMiddle EastAsia-Pacific
| Role group | Nov 2026 | Dec 2026 | Jan 2027 | Feb 2027 | Mar 2027 | Apr 2027 | May 2027 | Jun 2027 | Jul 2027 | Aug 2027 | Sep 2027 | Oct 2027 | Nov 2027 | Dec 2027 | Jan 2028 | Feb 2028 | Mar 2028 | Apr 2028 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Project management & controls | 5 announced· +134 estimated | 4 announced· +131 estimated | 4 announced· +131 estimated | 4 announced· +130 estimated | 4 announced· +130 estimated | 4 announced· +129 estimated | 4 announced· +128 estimated | 3 announced· +127 estimated | 3 announced· +125 estimated | 3 announced· +125 estimated | 3 announced· +122 estimated | 3 announced· +118 estimated | 3 announced· +46 estimated | 3 announced· +44 estimated | 3 announced· +37 estimated | 3 announced· +36 estimated | 3 announced· +21 estimated | 3 announced· +17 estimated |
| Engineering & design | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +94 estimated | 2 announced· +92 estimated | 2 announced· +90 estimated | 2 announced· +19 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +18 estimated | 2 announced· +4 estimated | 2 announced· +3 estimated |
| Construction & supervision | 38 announced· +38 estimated | 16 announced· +35 estimated | 12 announced· +35 estimated | 17 announced· +35 estimated | 25 announced· +35 estimated | 39 announced· +34 estimated | 62 announced· +33 estimated | 54 announced· +32 estimated | 49 announced· +30 estimated | 42 announced· +30 estimated | 37 announced· +30 estimated | 31 announced· +29 estimated | 13 announced· +28 estimated | 5 announced· +26 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +17 estimated | 2 announced· +14 estimated |
| Commissioning & start-up | 2 announced· +10 estimated | 1 announced· +9 estimated | 1 announced· +9 estimated | 1 announced· +8 estimated | 1 announced· +8 estimated | 1 announced· +8 estimated | 1 announced· +7 estimated | +6 estimated | +6 estimated | +6 estimated | +4 estimated | |||||||
| QA/QC & HSE | 4 announced· +41 estimated | 3 announced· +38 estimated | 3 announced· +38 estimated | 3 announced· +37 estimated | 3 announced· +37 estimated | 3 announced· +36 estimated | 3 announced· +35 estimated | 2 announced· +34 estimated | 2 announced· +32 estimated | 2 announced· +32 estimated | 2 announced· +31 estimated | 2 announced· +29 estimated | 2 announced· +28 estimated | 2 announced· +26 estimated | 2 announced· +19 estimated | 2 announced· +18 estimated | 2 announced· +17 estimated | 2 announced· +14 estimated |
| Document control & support | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +99 estimated | 3 announced· +98 estimated | 3 announced· +96 estimated | 3 announced· +96 estimated | 3 announced· +93 estimated | 3 announced· +91 estimated | 3 announced· +20 estimated | 3 announced· +20 estimated | 3 announced· +19 estimated | 3 announced· +19 estimated | 3 announced· +5 estimated | 3 announced· +4 estimated |
How we count
Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.
How the radar works.
One admission rule: an item must say where work is coming, for whom and when.
Sourced
Every item links to where it was published: a grid operator, a government agency, a company or the trade press. The summary is in our own words. A date is either the source's publication date, the event date it states, or — when a page carries no date — the day we last checked it, and we say which.
Admission
A collector reads a short list of public feeds a few times a day, respects robots.txt and keeps headlines only. An item is admitted only if it answers where work is coming, for whom and when, passes two independent checks, carries a date and a source we know, and is written in our own words. Market and price news is not admitted. Anything those checks cannot settle waits for a person.
Discipline matches are our inference
Company, yard, area and sector matches are facts from the source. Discipline matches are not: they come from our mapping of role families to project phases — for example estimating before a tender, commissioning near start-up. It is not a vacancy count.
The same items feed The North Sea, live. To add a company, yard or area to the list: contact us.