Project · Offshore wind · United States
Coastal Virginia Offshore Wind (CVOW)
The largest offshore wind farm under construction in the US, and a live example of political/regulatory risk hitting an in-progress project — a case study for how fast schedules and crew mobilisation can move when a stop-work order lands and lifts within weeks.
Checked by hand against the sources below (2026-10-20).
- Engineering (done)
- Fabrication (done)
- Transport & installation (now)
- Hook-up
- Commissioning (now)
- Operation (next)
Now Transport & installation · Commissioning (reported: installation (approx. 81% complete as of 31 July 2026; 31 turbines installed and 32nd underway; first power to the grid March 2026; two of…)
Next Operation · not announced
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- Dominion EnergyOperator / ownerdeveloper/owner; Dominion’s timeline identifies Charybdis as the Jones Act-compliant vessel installing the first commercial-project turbine in January 2026.…
- Siemens GamesaEquipment & supplyturbine supplier — 176 x SG 14-222 DD, 14.6 MW turbines
- Kind
- Offshore wind
- Country
- United States
- Size
- 2.6 GW, 176 turbines, 3 offshore substations
- Operator
- Dominion Energy
- Position
- 36.97°N 75.35°W, approximate
On the Radar each linked to its source
Sources
- Dominion says Coastal Virginia Offshore Wind project tops 70% complete as turbine installation enters slower final stretchPower Engineering · published 2026 · read 2026-09-19
- U.S. District Court grants preliminary injunction allowing Coastal Virginia Offshore Wind project to resume workDominion Energy (company newsroom) · published 2026 · read 2026-09-19
- Work resumes on Coastal Virginia Offshore Wind project after court order ends federal pauseVirginia Mercury · published 2026-01-20 · read 2026-09-19
- Largest US Offshore Wind Farm 81 Pct Complete, Final Turbine Expected by End of 2027offshoreWIND.biz · published 2026-08-03 · read 2026-10-08
- Coastal Virginia Offshore Wind begins delivering powerUtility Dive · published 2026-03-26 · read 2026-10-08
- 5 offshore wind farms move ahead after Trump admin misses appeal deadlineElectrek · published 2026-04-10 · read 2026-10-08
- Project TimelineDominion Energy / CVOW · read 2026-10-20
- Resource LibraryDominion Energy / CVOW · read 2026-10-20
- Dominion Energy Announces Second-Quarter 2026 ResultsDominion Energy · published 2026-07-31 · read 2026-10-20