Energy & offshore tender calendar 2026–2028

Tender, licensing and allocation rounds for offshore wind, grids, oil and gas, CCS and hydrogen, worldwide, as officially scheduled. Dates as published by the authority named; checked on 8 Oct 2026; changes are common — always check the source.

Official schedules only. A round announced without dates is listed as announced, with “not published” where the authority has given no date. This is not a complete list of every round in every country.

Add to calendar (.ics)Real dates only; quarters are left out of the file.

Jump to the timeline

Timeline

Africa

Each region opens and closes. A period the source gives only as a quarter, half year or year is drawn hollow across that period. Rows link to the entry below.

Africa

Only licensing rounds for which the state agency itself publishes dates. Rounds reported in the trade press without an official schedule are left out.

Oil & gas licensingclosed

Nigeria 2025 Licensing Round

Nigeria · NUPRC licensing rounds

Window
1 Dec 2025 – 12 Jun 2026
Award expected
not published
Authority
NUPRC
Capacity / scope
50 blocks offered; 37 blocks with winning bidders

Bid submission ran to 12 June 2026; at the commercial bid conference on 21 July 2026 NUPRC named 31 companies as winners of 37 blocks; final award follows signature bonus payment and ministerial approval.

Source

checked on 8 Oct 2026

Oil & gas licensingopen

Algeria Bid Round 2026

Algeria · ALNAFT bid rounds

Window
19 Apr 2026 – 26 Nov 2026
Award expected
31 Jan 2027
Authority
ALNAFT
Capacity / scope
7 perimeters

Launched 19 April 2026 with seven onshore perimeters; bids due 26 November 2026; results are to be announced before contract signing with Sonatrach planned for 31 January 2027.

Source

checked on 8 Oct 2026

Oil & gas licensingopen

Nigeria 2026 Licensing Round

Nigeria · NUPRC licensing rounds

Window
opens 6 Oct 2026
Award expected
not published
Authority
NUPRC
Capacity / scope
40 blocks (land, shallow water and deep water)

Formally launched on 6 October 2026 with presidential/ministerial approval, offering 40 blocks across land, shallow water and deep water. NUPRC says full block details, qualification requirements and participation procedures will be published on its website and a dedicated licensing-round portal in the coming days; guidelines will publish the evaluation methodology and require beneficial-ownership disclosure. No bid deadline published yet.

Source

checked on 8 Oct 2026

After an award: the usual order of work

General sequence, not a forecast for any round listed here.

  • Offshore wind. Site award → developer's engineering and contracting → fabrication of foundations, cables and turbines → offshore installation → commissioning.
  • Grid & HVDC. Framework or platform award → detailed engineering → fabrication of jackets, topsides and cables → transport and installation → commissioning.
  • Oil & gas licensing. Licence award → seismic and exploration drilling → appraisal → field development decision → engineering, fabrication and installation, if a discovery is developed.