Radar

Energy & offshore tender calendar 2026–2028

Tender, licensing and allocation rounds for offshore wind, grids, oil and gas, CCS and hydrogen, worldwide, as officially scheduled. Dates as published by the authority named; checked on 8 Oct 2026; changes are common — always check the source.

Official schedules only. A round announced without dates is listed as announced, with “not published” where the authority has given no date. This is not a complete list of every round in every country.

Add to calendar (.ics)Real dates only; quarters are left out of the file.

Jump to the timeline

Timeline

North Sea & NW Europe
2026Q1Q2Q3Q42027Q1Q2Q3Q42028Q1Q2Q3Q4Nederwiek I-A site permitNederwiek I-A site permitNetherlandsdates outside 2026–2028, see the entryHesselø (Kattegat) offshore wind tend…Hesselø (Kattegat) offshore wind tender with two-sided CfDDenmarkWindow: 20 Nov 2025 – 20 May 2026Awarded: 4 Aug 2026Nordsøen I Midt offshore wind tender…Nordsøen I Midt offshore wind tender with two-sided CfDDenmarkWindow: 20 Nov 2025 – 20 May 2026Awarded: 4 Aug 2026Nordsøen I Syd offshore wind tender w…Nordsøen I Syd offshore wind tender with two-sided CfDDenmarkWindow: 20 Nov 2025 – 23 Oct 2028CfD Allocation Round 7 - offshore win…CfD Allocation Round 7 - offshore wind and floating offshore wind resultsUnited KingdomAwarded: 14 Jan 2026Offshore Wind Leasing Round 5 - Celti…Offshore Wind Leasing Round 5 - Celtic Sea floating wind, third siteUnited KingdomAwarded: 3 Mar 2026France offshore wind tender AO10 (ele…France offshore wind tender AO10 (eleven projects, fixed and floating)FranceWindow: Jun 2026 – 12 Oct 2026Award expected: Feb 2027CfD Allocation Round 8 - all technolo…CfD Allocation Round 8 - all technologies incl. offshore windUnited KingdomWindow: 20 Jul 2026 – 7 Aug 2026Morgan offshore wind site tender - Ir…Morgan offshore wind site tender - Irish Sea, re-tender of a Round 4 siteUnited KingdomWindow: 24 Jul 2026 – 4 Sep 2026Award expected: Q4 2026IJmuiden Ver Gamma-A site permit with…IJmuiden Ver Gamma-A site permit with subsidyNetherlandsWindow: 26 Nov 2026 – 10 Dec 2026Award expected: Q1 2027IJmuiden Ver Gamma-B site permit with…IJmuiden Ver Gamma-B site permit with subsidyNetherlandsWindow: 26 Nov 2026 – 10 Dec 2026Award expected: Q1 2027Germany offshore wind site tender 202…Germany offshore wind site tender 2027 (N-10.1, N-10.2, N-12.4, N-12.5, N-13.1, N-13.2)GermanyWindow: opens 2027Offshore Wind Leasing Round 6 - mainl…Offshore Wind Leasing Round 6 - mainly North East England, fixed-bottomUnited KingdomWindow: opens H1 2027Germany offshore wind site tender 202…Germany offshore wind site tender 2028 (N-6.8, N-9.5)GermanyWindow: opens 2028Belgium Princess Elisabeth Zone, firs…Belgium Princess Elisabeth Zone, first lot (PEZ 1) offshore wind tender relaunchBelgiumdates not publishedDoordewind I and II site permitsDoordewind I and II site permitsNetherlandsdates not publishedFirst Dutch offshore wind round under…First Dutch offshore wind round under two-way contracts (CfD)Netherlandsdates not publishedNederwiek I-B, II and III site permitsNederwiek I-B, II and III site permitsNetherlandsdates not publishedTen noorden van de Waddeneilanden I a…Ten noorden van de Waddeneilanden I and Hollandse Kust (west) VIII site permitsNetherlandsdates not publishedUtsira Nord floating wind - state aid…Utsira Nord floating wind - state aid competition after maturation phaseNorwaydates not publishedtoday · 12 Oct 2026
Baltic & Poland
Americas
Asia-Pacific

Each region opens and closes. A period the source gives only as a quarter, half year or year is drawn hollow across that period. Rows link to the entry below.

North Sea & NW Europe

Netherlands, United Kingdom, Germany, Denmark, Norway, Belgium and France: official schedules only. Rounds announced without dates are listed as announced. Grid and HVDC award rounds appear only where the TSO or regulator has published a schedule; most have not.

Offshore windclosed

Nederwiek I-A site permit

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
16 Oct 2025 – 30 Oct 2025
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW

The October 2025 round closed without applications; RVO's planning table lists the new permit procedure for this site as to be determined.

Source

checked on 8 Oct 2026

Offshore windawarded

Hesselø (Kattegat) offshore wind tender with two-sided CfD

Denmark · Danish 3 GW offshore wind tenders with state support

Window
20 Nov 2025 – 20 May 2026
Awarded
4 Aug 2026
Authority
Energistyrelsen (Danish Energy Agency)
Capacity / scope
minimum 800 MW (0.8-1.2 GW depending on design)

Awarded on 2026-08-04 to Vattenfall Vindkraft Offshore Wind DK P/S at 542 DKK/MWh; the agency reports five bids; commissioning required by end of 2032.

Source

checked on 8 Oct 2026

Offshore windawarded

Nordsøen I Midt offshore wind tender with two-sided CfD

Denmark · Danish 3 GW offshore wind tenders with state support

Window
20 Nov 2025 – 20 May 2026
Awarded
4 Aug 2026
Authority
Energistyrelsen (Danish Energy Agency)
Capacity / scope
minimum 1 GW

Awarded on 2026-08-04 to Vattenfall Vindkraft A/S (on behalf of a company to be formed) at 504 DKK/MWh; the agency reports two bids; commissioning required by end of 2032.

Source

checked on 8 Oct 2026

Offshore windopen

Nordsøen I Syd offshore wind tender with two-sided CfD

Denmark · Danish 3 GW offshore wind tenders with state support

Window
20 Nov 2025 – 23 Oct 2028
Award expected
not published
Authority
Energistyrelsen (Danish Energy Agency)
Capacity / scope
minimum 1 GW

Tender opened 2025-11-20 together with Midt and Hesselø; bid deadline 2028-10-23; commissioning required by end of 2034; support cap of DKK 55.2 bn covers all three parks.

Source

checked on 8 Oct 2026

Offshore windawarded

CfD Allocation Round 7 - offshore wind and floating offshore wind results

United Kingdom · UK Contracts for Difference

Window
not published
Awarded
14 Jan 2026
Authority
DESNZ / NESO
Capacity / scope
Pot 3 offshore wind projects totalling 8,245 MW and Pot 4 floating offshore wind 192.5 MW (sum of project sizes in the results notice)

Awarded on 2026-01-14: DESNZ published the Pot 3 and Pot 4 outcome as NESO notified applicants; ten fixed-bottom CfD units and two floating projects (Erebus, Pentland) listed.

Source

checked on 8 Oct 2026

Offshore windawarded

Offshore Wind Leasing Round 5 - Celtic Sea floating wind, third site

United Kingdom · The Crown Estate offshore wind leasing

Window
not published
Awarded
3 Mar 2026
Authority
The Crown Estate
Capacity / scope
1.5 GW (third site); up to 4.5 GW across three sites

Ocean Winds named for the third site on 2025-11-19 via direct award and entered the agreement for lease announced 2026-03-03; the other two sites (Equinor, Gwynt Glas) signed in October 2025.

Source

checked on 8 Oct 2026

Offshore windopen

France offshore wind tender AO10 (eleven projects, fixed and floating)

France · France offshore wind tenders (PPE2/PPE3)

Window
Jun 2026 – 12 Oct 2026
Award expected
Feb 2027
Authority
Ministry in charge of energy (DGEC) / CRE
Capacity / scope
approx. 10 GW (approx. 5 GW fixed, approx. 5 GW floating)

Tender no. 1/2026 covers eleven projects off Normandy, Brittany, the South Atlantic coast and in the Mediterranean; projects first planned under AO9 were folded into AO10; bids due 12 Oct 2026 12:00 Paris time; CRE published amended specifications on 20 Aug, 24 Sep and 7 Oct 2026; ministry states award in February 2027.

Source

checked on 8 Oct 2026

Offshore windclosed

CfD Allocation Round 8 - all technologies incl. offshore wind

United Kingdom · UK Contracts for Difference

Window
20 Jul 2026 – 7 Aug 2026
Award expected
not published
Authority
DESNZ / NESO / LCCC
Capacity / scope
not published

Application window ran 20 July-7 August 2026; the indicative timetable puts NESO result notification between 27 Nov-1 Dec 2026 (no appeals) and 15-17 Feb 2027 (Tier 2 appeals), depending on the qualification scenario.

Source

checked on 8 Oct 2026

Offshore windclosed

Morgan offshore wind site tender - Irish Sea, re-tender of a Round 4 site

United Kingdom · The Crown Estate offshore wind leasing

Window
24 Jul 2026 – 4 Sep 2026
Award expected
Q4 2026
Authority
The Crown Estate
Capacity / scope
up to 1.5 GW

Accelerated re-tender of the Round 4 site discontinued in January 2026; offers a 10-year agreement for lease with the windfarm DCO (August 2025) and a NESO grid connection agreement in place. Open to sole bidders or consortia registered on The Crown Estate e-tendering portal; one questionnaire submission each, due 4 September 2026, decides entry to an ascending clock auction on a Site Exclusivity Fee paid over 20 years from lease. The 24 July notice was replaced on 27 July by a competitive flexible procedure notice with unchanged deadlines; Find a Tender gives 20 November 2026 as the estimated award decision date; The Crown Estate expects the auction and selection of a preferred bidder towards the end of 2026.

Source

checked on 8 Oct 2026

Offshore windannounced

IJmuiden Ver Gamma-A site permit with subsidy

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
26 Nov 2026 – 10 Dec 2026
Award expected
Q1 2027
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW

Permit with subsidy or a subsidy-free bid, both procedures run at the same time; maximum tender amount EUR 0.117 per kWh; RVO expects the wind farm to be operational in 2032.

Source

checked on 8 Oct 2026

Offshore windannounced

IJmuiden Ver Gamma-B site permit with subsidy

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
26 Nov 2026 – 10 Dec 2026
Award expected
Q1 2027
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW

Added to the 2026 round by government decision in April 2026; maximum tender amount EUR 0.116 per kWh; RVO expects the wind farm to be operational in 2032.

Source

checked on 8 Oct 2026

Offshore windpostponed

Germany offshore wind site tender 2027 (N-10.1, N-10.2, N-12.4, N-12.5, N-13.1, N-13.2)

Germany · WindSeeG offshore wind site tenders

Window
opens 2027
Award expected
not published
Authority
Bundesnetzagentur / BSH
Capacity / scope
N-10.1 2,000 MW; N-10.2 500 MW; N-12.4 1,000 MW; N-12.5 1,000 MW; N-13.1 500 MW; N-13.2 1,000 MW (expected capacity per BSH site development plan)

Tenders planned for 2026 were moved to tender year 2027 after the cabinet decision of 28 Jan 2026; no bid date published; N-10.1 and N-10.2 received no bids on 1 Aug 2025. On 2 Sep 2026 the cabinet adopted a WindSeeG amendment bill (Bundestag Drucksache 21/8238, first reading 8 Oct 2026, not yet law): a two-stage award procedure (first subsidy-free, then a two-sided contract for difference), an annual tender corridor of 2,000-4,800 MW from 2027, a 35-year operating period, and the option for the site development plan to set a different bid date.

Source

checked on 8 Oct 2026

Offshore windannounced

Offshore Wind Leasing Round 6 - mainly North East England, fixed-bottom

United Kingdom · The Crown Estate offshore wind leasing

Window
opens H1 2027
Award expected
not published
Authority
The Crown Estate
Capacity / scope
approximately 6 GW or more

The Crown Estate intends to launch the round in the first half of 2027 after market engagement; capacity and sites remain subject to stakeholder engagement and NESO network plans.

Source

checked on 8 Oct 2026

Offshore windannounced

Germany offshore wind site tender 2028 (N-6.8, N-9.5)

Germany · WindSeeG offshore wind site tenders

Window
opens 2028
Award expected
not published
Authority
Bundesnetzagentur / BSH
Capacity / scope
N-6.8 2,000 MW; N-9.5 1,000 MW (expected capacity per BSH site development plan)

The amended site development plan of 30 Jan 2026 sets tender year 2028 for N-6.8 (moved from 2027) and N-9.5; no bid date published. A WindSeeG amendment bill adopted by the cabinet on 2 Sep 2026 (Drucksache 21/8238, not yet law) would introduce a two-stage subsidy-free/CfD award and a 2,000-4,800 MW annual corridor, and would form the basis for the next site development plan, which may re-cut sites.

Source

checked on 8 Oct 2026

Offshore windannounced

Belgium Princess Elisabeth Zone, first lot (PEZ 1) offshore wind tender relaunch

Belgium · Princess Elisabeth Zone tenders

Window
not published
Award expected
not published
Authority
Federal Minister of Energy / FPS Economy / CREG
Capacity / scope
not published

Previous tender cancelled in early July 2025; on 18 Jul 2026 the Council of Ministers approved the amended tender royal decree (two-sided CfD, five-year build period, no strike price cap); launch follows Council of State advice and EU state aid notification, no launch date given.

Source

checked on 8 Oct 2026

Offshore windannounced

Doordewind I and II site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 2 GW each

RVO's public planning table lists the tender/permit procedure for both sites as to be determined; the minister's 21 May 2026 letter to Parliament (Kamerstuk 33561, nr. 102) confirmed Doordewind kavel II's location in the development framework but left both kavels' delivery and tender dates unchanged pending the full roadmap update due end 2026.

Source

checked on 8 Oct 2026

Offshore windannounced

First Dutch offshore wind round under two-way contracts (CfD)

Netherlands · Dutch two-way contracts for offshore wind

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
not published

RVO states that the first offshore wind contracts for difference are planned to launch towards the end of 2027; no site or date published.

Source

checked on 8 Oct 2026

Offshore windannounced

Nederwiek I-B, II and III site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW (I-B); about 2 GW each (II, III)

RVO's planning table lists the permit procedure for these sites as to be determined.

Source

checked on 8 Oct 2026

Offshore windannounced

Ten noorden van de Waddeneilanden I and Hollandse Kust (west) VIII site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 0.7 GW each

RVO's planning table lists the permit procedure for both sites as to be determined; the roadmap map notes Ten noorden van de Waddeneilanden as a possible hydrogen demonstration site.

Source

checked on 8 Oct 2026

Offshore windannounced

Utsira Nord floating wind - state aid competition after maturation phase

Norway · Norway offshore wind area allocation

Window
not published
Award expected
not published
Authority
Energidepartementet / NVE
Capacity / scope
up to 500 MW per project area

Two project areas were awarded on 2025-12-11; NVE held a hearing on the study programmes until 2026-06-18; a later competition gives state aid to one rights holder, no date published.

Source

  • Utsira NordNVE (Norwegian Water Resources and Energy Directorate) · retrieved 20 Sep 2026

checked on 8 Oct 2026

Baltic & Poland

Official schedules only. Several Baltic Sea rounds were closed without award or have no new date; those are left out until the authority publishes one.

Offshore windannounced

Poland offshore wind CfD auction 2027 (phase II)

Poland · Poland Offshore Wind Act phase II auctions

Window
opens 2027
Award expected
not published
Authority
URE (Energy Regulatory Office) / Ministry of Climate and Environment
Capacity / scope
max. 4 GW

Statutory schedule sets the second phase II auction for 2027 with a maximum volume of 4 GW; the first auction was held on 17 Dec 2025 and awarded 3,435 MW to three projects; no 2027 auction date announced.

Source

checked on 8 Oct 2026

Americas

Official schedules only: federal and state agencies' own notices. Rounds announced without dates are listed as announced.

Offshore windannounced

Nova Scotia offshore wind Call for Bids NS25-1R

Canada · Canada-Nova Scotia offshore wind land tenure

Window
opens 2026
Award expected
not published
Authority
Canada-Nova Scotia Offshore Energy Regulator (CNSOER)
Capacity / scope
up to 5 GW

Prequalification ran 16 October 2025 to 13 January 2026; the province states the first call for bids comes in 2026 and the Premier said on 26 June 2026 it opens later this year; no bid deadline published.

Source

checked on 8 Oct 2026

Offshore windcancelled

United States federal offshore wind lease sales

United States · BOEM Outer Continental Shelf renewable energy leasing

Window
not published
Award expected
not published
Authority
Marine Minerals Administration (MMA, successor to BOEM/BSEE), U.S. Department of the Interior
Capacity / scope
not published

Offshore wind leasing is halted under a presidential memorandum; BOEM rescinded all designated Wind Energy Areas on 30 July 2025 and lists no lease sale schedule.

Source

checked on 8 Oct 2026

Asia-Pacific

Official schedules only, from the ministries and regulators named. Rounds announced without dates are listed as announced.

Offshore windclosed

Taiwan offshore wind zonal development, Round 3.3 capacity allocation

Taiwan · Taiwan offshore wind zonal development (Round 3)

Window
1 Apr 2026 – 30 Sep 2026
Award expected
2026
Authority
Ministry of Economic Affairs / Energy Administration
Capacity / scope
3.6 GW

Applications accepted 1 April to 30 September 2026; the ministry plans to complete selection and publish results before the end of 2026; grid connection 2030-2031. Trade press (UDN, 30 Sep 2026) reports the Energy Administration received two applications for two wind farms (CIP and Orsted), well short of the 3.6 GW on offer; no ministry release on the receipt count was found.

Source

checked on 8 Oct 2026

Offshore windpostponed

Philippines Green Energy Auction 5 (fixed-bottom offshore wind)

Philippines · Green Energy Auction Program (GEA)

Window
2 Mar 2026 – 1 Dec 2026
Award expected
not published
Authority
Department of Energy (DOE)
Capacity / scope
3,300 MW (delivery 2028-2030)

Launched 25 November 2025, supplier registration began 2 March 2026; DOE announced on 10 July 2026 that auction activities were temporarily on hold for a recalibration review. DOE's indicative timeline of 29 July 2026: department circular signed by 24 August and published early September; supplemental TOR released by 2 October 2026; qualified-bidder posting through Q4 2026; Auction Proper 1 December 2026; bid validation to certificates of award 2 December 2026 - 30 June 2027. DOE says all dates are indicative; no resumption notice or supplemental TOR found on doe.gov.ph as of 8 October 2026.

Source

checked on 8 Oct 2026

Offshore windawarded

South Korea offshore wind fixed-price contract tender, first half 2026

South Korea · Korea RPS fixed-price contract competitive bidding (wind)

Window
opens 30 Mar 2026
Awarded
30 Jun 2026
Authority
Ministry of Climate, Energy and Environment / Korea Energy Agency
Capacity / scope
1,800 MW tendered (1,400 MW fixed-bottom incl. 400 MW public-led, 400 MW floating); 1,786 MW selected

Tender notice published 30 March 2026; awarded on 30 June 2026, when the ministry reported five projects totalling 1,786 MW selected and pointed to a multi-year tender roadmap.

Source

checked on 8 Oct 2026

Offshore windannounced

Japan offshore wind operator tender, Round 4 (Hokkaido Matsumae and Hiyama promotion zones)

Japan · Japan Marine Renewable Energy Act operator tenders

Window
not published
Award expected
not published
Authority
METI / MLIT
Capacity / scope
not published

METI lists Hokkaido Matsumae and Hokkaido Hiyama as zones with pre-tender information provision; no tender start date is published, and no date for re-tendering the returned Round 1 zones was found.

Source

checked on 8 Oct 2026

After an award: the usual order of work

General sequence, not a forecast for any round listed here.

  • Offshore wind. Site award → developer's engineering and contracting → fabrication of foundations, cables and turbines → offshore installation → commissioning.
  • Grid & HVDC. Framework or platform award → detailed engineering → fabrication of jackets, topsides and cables → transport and installation → commissioning.
  • Oil & gas licensing. Licence award → seismic and exploration drilling → appraisal → field development decision → engineering, fabrication and installation, if a discovery is developed.
  • CCS & hydrogen. Support or licence award → final investment decision → engineering → construction → commissioning.