Offshore grid platform
IJmuiden Ver Gamma
Every fact below is as reported by the linked source, read on 19 Sep 2026. A field the source does not give says “not published”.
- Kind
- Offshore grid platform
- Capacity
- 2,000 MW
- Phase / status
- Under construction
- Operator
- TenneT
- Contractors
- GE Vernova-Seatrium consortium; jacket fabrication by Heerema Fabrication Group, Vlissingen
- Technology
- HVDC 525kV, 2GW programme
What’s next as of 19 Sep 2026
Jacket construction (ceremonial first steel cut, September 2026) under way at Heerema Vlissingen - the second of the three 2GW jackets built there; sail-out targeted summer 2028; commissioning targeted 2029.
Source retrieved 19 Sep 2026
reNEWS / Ocean Energy Resources (Sep 2026) · retrieved 19 Sep 2026 · Public information, fact reported with source
On the tender calendar
IJmuiden Ver Gamma-A site permit with subsidy (26 Nov 2026 – 10 Dec 2026), IJmuiden Ver Gamma-B site permit with subsidy (26 Nov 2026 – 10 Dec 2026)