Offshore grid platform

IJmuiden Ver Gamma

Every fact below is as reported by the linked source, read on 19 Sep 2026. A field the source does not give says “not published”.

Kind
Offshore grid platform
Capacity
2,000 MW
Phase / status
Under construction
Operator
TenneT
Contractors
GE Vernova-Seatrium consortium; jacket fabrication by Heerema Fabrication Group, Vlissingen
Technology
HVDC 525kV, 2GW programme

What’s next as of 19 Sep 2026

Jacket construction (ceremonial first steel cut, September 2026) under way at Heerema Vlissingen - the second of the three 2GW jackets built there; sail-out targeted summer 2028; commissioning targeted 2029.

Source retrieved 19 Sep 2026

reNEWS / Ocean Energy Resources (Sep 2026) · retrieved 19 Sep 2026 · Public information, fact reported with source

On the tender calendar

IJmuiden Ver Gamma-A site permit with subsidy (26 Nov 2026 – 10 Dec 2026), IJmuiden Ver Gamma-B site permit with subsidy (26 Nov 2026 – 10 Dec 2026)

53.02°N, 3.67°E. Position approximate: zone centroid approximate. Basemap: Natural Earth.