Kind
Offshore grid platform
Capacity
2,000 MW
Phase / status
Planned
Operator
TenneT
Contractors
GE Vernova-Seatrium consortium (converter stations); jacket fabrication contracted to Heerema Fabrication Group, Vlissingen (third of the three 2GW jackets there, after Beta and Gamma)
Technology
HVDC 525kV, 2GW programme

What’s next as of 19 Sep 2026

Jacket fabrication contracted to Heerema Vlissingen but not yet started as of this dataset's retrieval date; commissioning targeted 2031.

Source retrieved 19 Sep 2026

T&D World (2026) · retrieved 19 Sep 2026 · Public information, fact reported with source