Kaskida FPU (bp)
USA, Gulf of Mexico
bp's first 20k-psi development: a greenfield hub with FPU fabrication, subsea manufacturing and installation scheduled 2025–2029.
Size80,000 b/d FPU; six wells at 20,000 psi; first oil 2029
- FID
- Engineering
- Fabrication
- Construction (named in the reported phase)
- Installation
- Commissioning
Phase, as reported: FPU under construction at Seatrium
…
Who builds it
- bp operator
- Seatrium
- TechnipFMC
- SBM Offshore
- more under “More”
Reported risk bp is reportedly selling minority stakes in Kaskida and Tiber…
6 sources checked on 2026-10-08
More why we watch it · key dates · all contractors · sources
Why we watch it
bp's first 20k-psi development: a greenfield hub with FPU fabrication, subsea manufacturing and installation scheduled 2025–2029 — the design is to be repeated on Tiber.
Phase in full, as reported
FPU under construction at Seatrium (steel strike 3Q2025; 25-50% complete at end-June 2026, yard delivery scheduled 2027) and subsea manufacturing in progress towards first oil 2029
Reported risk in full, as reported
bp is reportedly selling minority stakes in Kaskida and Tiber. It would keep operatorship (Reuters, via Offshore Magazine, June 2026); no sale announced yet.
Who builds it as stated by the sources
Operator / developerbp (100% working interest)
- bpoperator and sole owner; bp's sixth production hub in the Gulf
- SeatriumEPC and onshore commissioning of the floating production unit — four-column semisubmersible hull with single topside module, integrated with Goliath twin cranes (Dec 2024)
- TechnipFMCintegrated EPCI for subsea production systems incl. 20,000-psi standardized trees and manifolds, plus umbilicals, risers and flowlines; 'substantial' award (US$250–500 m), Oct 2024
- SBM Offshorewet tow and installation of the semi-submersible FPU (Apr 2025)
- SLB OneSubseasubsea boosting (per OE Digital)
- Exmar Offshore / Audubon EngineeringFPU hull and topsides design engineering (per OE Digital)
Key dates as stated by the sources
- FID
- July 2024
- Technipfmc award
- 2024-10
- Seatrium EPC award
- 2024-12
- Sbm installation award
- 2025-04
- First oil target
- 2029
- Fpu steel strike
- 3Q2025
- Fpu yard delivery
- 2027 (Seatrium order book)
Disciplines likely needed our inference
- HPHT subsea engineers
- FPU topsides/hull engineers
- riser and flowline engineers
- commissioning engineers
- marine installation and HSE
Derived by us from project kind and phase - not stated by the sources below.
Sources checked on 2026-10-08
- Seatrium to perform EPC work for bp's Kaskida FPUOffshore Magazine · 2024-12-26
- BP Hires SBM Offshore to Install Kaskida FPU in Gulf of AmericaOE Digital · 2025-04-30
- TechnipFMC Scoops Kaskida Subsea WorkJPT (SPE) · 2024-10-09
- Seatrium 1H2026 Results presentation (order book project table)Seatrium Limited (SGX filing) · 2026-07-31
- Seatrium Continues Strong Momentum into 3Q2025 (business update)Seatrium Limited (investor newsroom PDF) · 2025-11-13
- bp reportedly initiates sale of minority interests in Kaskida, Tiber projectsOffshore Magazine · 2026-06-16
Position on the globe: 26.90°N 92.90°W. Location approximate: Keathley Canyon Block 292, ~250 miles (400 km) south-west of New Orleans; water depth ~6,000 ft (1,830 m).
This project on its own page - facts, sources and a summary to share.