Project · Offshore gas platforms · Norway
Yggdrasil (Aker BP)
A three-platform development now estimated at NOK 195 bn (nominal, Oct 2026): the last topsides go offshore in late 2026, with hook-up, commissioning and subsea installation running into 2027.
Checked by hand against the sources below (2026-10-20).
- Engineering (done)
- Fabrication (done)
- Transport & installation (now)
- Hook-up (now)
- Commissioning (next)
- Operation
Now Transport & installation · Hook-up (reported: offshore installation and hook-up (Hugin B topside installed early July 2026; Munin topside loaded out at Aibel Haugesund, ready for…)
Next Commissioning · not announced
Roles Commissioning & start-up · QA/QC & HSE · Project management & controls · Role groups per phase: our planning assumption from the Crew Forecast model.
Later Operation summer 2027 (start-up target 2027 (Aker BP aims for summer 2027), as reported)
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- Aker BPOperator / owneroperator (Hugin licence 76.72%); partners Equinor and Orlen Upstream Norway
- Aker SolutionsEPC / main contractorEPC and offshore hook-up for the Hugin A production platform and jacket and the Hugin B unmanned wellhead platform and jacket (contract ~NOK 22 bn, Dec 2022);…
- Subsea7Transport & installationSURF package (per Offshore Technology project profile)
- AllseasTransport & installationtopsides installation (per Offshore Technology project profile)
- NKTEquipment & supplysubsea power cables (per Offshore Technology project profile)
- AibelEPC / main contractorEPC of the Munin unmanned production platform topsides (Haugesund)
- Kind
- Offshore gas platforms
- Country
- Norway
- Size
- ~700 million boe; 57 wells on three platforms; 250 km power cable from shore
- Operator
- Aker BP
- Position
- 59.90°N 2.20°E, approximate
Sources
- Aker BP sends Hugin B topside to Yggdrasil in the Norwegian North SeaPortNews · published 2026-07-06 · read 2026-09-22
- Aker Solutions Secures Multiple Contracts with Aker BP – Record High Order IntakeAker Solutions (company newsroom) · published 2022-12-16 · read 2026-09-22
- Yggdrasil Field Development, North Sea, NorwayOffshore Technology · read 2026-09-22
- Aker BP increases project cost estimates to protect 2027 startupsOil & Gas Journal · published 2026-07-15 · read 2026-10-08
- Aker BP narrows 2026 production guidance as major Norway projects advanceWorld Oil · published 2026-07-15 · read 2026-10-08
- Mammoet completes critical topsides operations for Aker BP's Yggdrasil projectWorld Oil · published 2026-08-13 · read 2026-10-08
- Costs of Aker BP's flagship offshore projects continue to rise (Reuters)Baird Maritime · published 2026-10-07 · read 2026-10-08
- Second quarter 2026 resultsAker BP · published 2026-07-15 · read 2026-10-20
- Yggdrasil-områdetAker BP · read 2026-10-20
- Field Fulla - Approved for productionSodir FactPages · published 2026-10-23 · read 2026-10-24
- Field Hugin - Approved for productionSodir FactPages · published 2026-04-19 · read 2026-10-24
- Field Hugin Satellitter - Approved for productionSodir FactPages · published 2026-04-02 · read 2026-10-24
- Field Munin - Approved for productionSodir FactPages · published 2026-10-23 · read 2026-10-24