Project · Offshore wind · Japan
Oga–Katagami–Akita offshore wind farm (315 MW, Round 2)
First deployment of 15 MW-class turbines in Japan, installed by a DEME-affiliated jack-up in 2027; foundation, turbine installation and marine coordination work runs 2026–2028.
Checked by hand against the sources below (2026-10-20).
- Engineering (done)
- Fabrication (now)
- Transport & installation (next)
- Hook-up
- Commissioning
- Operation
Now Fabrication (reported: construction / pre-installation (turbine deliveries from 2026; offshore installation second half of 2027; full commissioning June 2028))
Next Transport & installation · H2 2027 (offshore turbine installation scheduled second half of 2027, as reported)
Roles Project management & controls · Construction & supervision · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.
Later Operation June 2028 (planned commercial operation 30 June 2028, as reported)
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- Oga Katagami Akita Offshore Green Energy LLCOperator / owneroperator / developer
- DEMETransport & installationEngineering works and vessel charter for offshore installation of the 21 wind turbines using the jack-up vessel Sea Challenger under Japanese flag; offshore…
- Penta-Ocean ConstructionTransport & installationNamed alongside the project company as the contracting party for the turbine-installation package
- VestasEquipment & supplyTurbine supplier: 21 x V236-15.0 MW (selected 2024; deliveries from 2026)
- Kajima CorporationTransport & installationmanufacturing, procurement, transport and installation of the turbine foundations (contract October 2025)
- JFE EngineeringTransport & installationmanufactures and transports the 21 monopiles and transition pieces at its Kasaoka plant, January 2026 to March 2027; first monopile completed August 2026
- Kind
- Offshore wind
- Country
- Japan
- Size
- 315 MW; 21 x Vestas V236-15.0 MW; commissioning June 2028
- Operator
- Oga Katagami Akita Offshore Green Energy LLC
- Position
- 39.85°N 139.90°E, approximate
Sources
- DEME wins contract for offshore wind project in JapanDEME (company newsroom) · published 2026-05-29 · read 2026-10-20
- DEME to Install 15 MW Vestas Turbines at Japanese Offshore Wind FarmoffshoreWIND.biz · published 2026-05-29 · read 2026-09-22
- JFE Engineering Rolls Out First 'Made in Japan' Monopile for Oga–Katagami–Akita Offshore Wind FarmoffshoreWIND.biz · published 2026-08-27 · read 2026-10-08
- Japan's Oga–Katagami–Akita Offshore Wind Project Receives CertificationoffshoreWIND.biz · published 2026-07-22 · read 2026-10-08
- Japan's first order received for domestic monopile production for large-scale offshore wind power project in general watersJFE Engineering (company newsroom) · published 2025-12-26 · read 2026-10-08
- Kajima Inks Foundation Contract for 315 MW Japanese Offshore Wind FarmoffshoreWIND.biz · published 2025-10-23 · read 2026-10-08
- Project OverviewOga Katagami Akita Offshore Green Energy LLC · read 2026-10-20
- Presentation at the 10th Offshore Wind Power Seminar (Event Date: October 9, 2026)Oga Katagami Akita Offshore Green Energy LLC · published 2026-10-13 · read 2026-10-20
- FY2025 Consolidated Financial ResultsJERA · published 2026-04-27 · read 2026-10-20