Radar

Energy & offshore tender calendar 2026–2028

Tender, licensing and allocation rounds for offshore wind, grids, oil and gas, CCS and hydrogen, worldwide, as officially scheduled. Dates as published by the authority named; checked on 8 Oct 2026; changes are common — always check the source.

Official schedules only. A round announced without dates is listed as announced, with “not published” where the authority has given no date. This is not a complete list of every round in every country.

Add to calendar (.ics)Real dates only; quarters are left out of the file.

Jump to the timeline

Timeline

North Sea & NW Europe

Each region opens and closes. A period the source gives only as a quarter, half year or year is drawn hollow across that period. Rows link to the entry below.

North Sea & NW Europe

Netherlands, United Kingdom, Germany, Denmark, Norway, Belgium and France: official schedules only. Rounds announced without dates are listed as announced. Grid and HVDC award rounds appear only where the TSO or regulator has published a schedule; most have not.

Offshore windannounced

IJmuiden Ver Gamma-A site permit with subsidy

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
26 Nov 2026 – 10 Dec 2026
Award expected
Q1 2027
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW

Permit with subsidy or a subsidy-free bid, both procedures run at the same time; maximum tender amount EUR 0.117 per kWh; RVO expects the wind farm to be operational in 2032.

Source

checked on 8 Oct 2026

Offshore windannounced

IJmuiden Ver Gamma-B site permit with subsidy

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
26 Nov 2026 – 10 Dec 2026
Award expected
Q1 2027
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW

Added to the 2026 round by government decision in April 2026; maximum tender amount EUR 0.116 per kWh; RVO expects the wind farm to be operational in 2032.

Source

checked on 8 Oct 2026

Offshore windannounced

Offshore Wind Leasing Round 6 - mainly North East England, fixed-bottom

United Kingdom · The Crown Estate offshore wind leasing

Window
opens H1 2027
Award expected
not published
Authority
The Crown Estate
Capacity / scope
approximately 6 GW or more

The Crown Estate intends to launch the round in the first half of 2027 after market engagement; capacity and sites remain subject to stakeholder engagement and NESO network plans.

Source

checked on 8 Oct 2026

Offshore windannounced

Germany offshore wind site tender 2028 (N-6.8, N-9.5)

Germany · WindSeeG offshore wind site tenders

Window
opens 2028
Award expected
not published
Authority
Bundesnetzagentur / BSH
Capacity / scope
N-6.8 2,000 MW; N-9.5 1,000 MW (expected capacity per BSH site development plan)

The amended site development plan of 30 Jan 2026 sets tender year 2028 for N-6.8 (moved from 2027) and N-9.5; no bid date published. A WindSeeG amendment bill adopted by the cabinet on 2 Sep 2026 (Drucksache 21/8238, not yet law) would introduce a two-stage subsidy-free/CfD award and a 2,000-4,800 MW annual corridor, and would form the basis for the next site development plan, which may re-cut sites.

Source

checked on 8 Oct 2026

Offshore windannounced

Belgium Princess Elisabeth Zone, first lot (PEZ 1) offshore wind tender relaunch

Belgium · Princess Elisabeth Zone tenders

Window
not published
Award expected
not published
Authority
Federal Minister of Energy / FPS Economy / CREG
Capacity / scope
not published

Previous tender cancelled in early July 2025; on 18 Jul 2026 the Council of Ministers approved the amended tender royal decree (two-sided CfD, five-year build period, no strike price cap); launch follows Council of State advice and EU state aid notification, no launch date given.

Source

checked on 8 Oct 2026

Offshore windannounced

Doordewind I and II site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 2 GW each

RVO's public planning table lists the tender/permit procedure for both sites as to be determined; the minister's 21 May 2026 letter to Parliament (Kamerstuk 33561, nr. 102) confirmed Doordewind kavel II's location in the development framework but left both kavels' delivery and tender dates unchanged pending the full roadmap update due end 2026.

Source

checked on 8 Oct 2026

Offshore windannounced

First Dutch offshore wind round under two-way contracts (CfD)

Netherlands · Dutch two-way contracts for offshore wind

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
not published

RVO states that the first offshore wind contracts for difference are planned to launch towards the end of 2027; no site or date published.

Source

checked on 8 Oct 2026

Offshore windannounced

Nederwiek I-B, II and III site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 1 GW (I-B); about 2 GW each (II, III)

RVO's planning table lists the permit procedure for these sites as to be determined.

Source

checked on 8 Oct 2026

Offshore windannounced

Ten noorden van de Waddeneilanden I and Hollandse Kust (west) VIII site permits

Netherlands · Dutch Offshore Wind Energy Roadmap

Window
not published
Award expected
not published
Authority
RVO / Ministry of Climate Policy and Green Growth (KGG)
Capacity / scope
about 0.7 GW each

RVO's planning table lists the permit procedure for both sites as to be determined; the roadmap map notes Ten noorden van de Waddeneilanden as a possible hydrogen demonstration site.

Source

checked on 8 Oct 2026

Offshore windannounced

Utsira Nord floating wind - state aid competition after maturation phase

Norway · Norway offshore wind area allocation

Window
not published
Award expected
not published
Authority
Energidepartementet / NVE
Capacity / scope
up to 500 MW per project area

Two project areas were awarded on 2025-12-11; NVE held a hearing on the study programmes until 2026-06-18; a later competition gives state aid to one rights holder, no date published.

Source

  • Utsira NordNVE (Norwegian Water Resources and Energy Directorate) · retrieved 20 Sep 2026

checked on 8 Oct 2026

After an award: the usual order of work

General sequence, not a forecast for any round listed here.

  • Offshore wind. Site award → developer's engineering and contracting → fabrication of foundations, cables and turbines → offshore installation → commissioning.
  • Grid & HVDC. Framework or platform award → detailed engineering → fabrication of jackets, topsides and cables → transport and installation → commissioning.
  • Oil & gas licensing. Licence award → seismic and exploration drilling → appraisal → field development decision → engineering, fabrication and installation, if a discovery is developed.
  • CCS & hydrogen. Support or licence award → final investment decision → engineering → construction → commissioning.