Energy & offshore tender calendar 2026–2028

Tender, licensing and allocation rounds for offshore wind, grids, oil and gas, CCS and hydrogen, worldwide, as officially scheduled. Dates as published by the authority named; checked on 8 Oct 2026; changes are common — always check the source.

Official schedules only. A round announced without dates is listed as announced, with “not published” where the authority has given no date. This is not a complete list of every round in every country.

Add to calendar (.ics)Real dates only; quarters are left out of the file.

Jump to the timeline

Timeline

Asia-Pacific

Each region opens and closes. A period the source gives only as a quarter, half year or year is drawn hollow across that period. Rows link to the entry below.

Asia-Pacific

Official schedules only, from the ministries and regulators named. Rounds announced without dates are listed as announced.

Offshore windclosed

Taiwan offshore wind zonal development, Round 3.3 capacity allocation

Taiwan · Taiwan offshore wind zonal development (Round 3)

Window
1 Apr 2026 – 30 Sep 2026
Award expected
2026
Authority
Ministry of Economic Affairs / Energy Administration
Capacity / scope
3.6 GW

Applications accepted 1 April to 30 September 2026; the ministry plans to complete selection and publish results before the end of 2026; grid connection 2030-2031. Trade press (UDN, 30 Sep 2026) reports the Energy Administration received two applications for two wind farms (CIP and Orsted), well short of the 3.6 GW on offer; no ministry release on the receipt count was found.

Source

checked on 8 Oct 2026

Offshore windpostponed

Philippines Green Energy Auction 5 (fixed-bottom offshore wind)

Philippines · Green Energy Auction Program (GEA)

Window
2 Mar 2026 – 1 Dec 2026
Award expected
not published
Authority
Department of Energy (DOE)
Capacity / scope
3,300 MW (delivery 2028-2030)

Launched 25 November 2025, supplier registration began 2 March 2026; DOE announced on 10 July 2026 that auction activities were temporarily on hold for a recalibration review. DOE's indicative timeline of 29 July 2026: department circular signed by 24 August and published early September; supplemental TOR released by 2 October 2026; qualified-bidder posting through Q4 2026; Auction Proper 1 December 2026; bid validation to certificates of award 2 December 2026 - 30 June 2027. DOE says all dates are indicative; no resumption notice or supplemental TOR found on doe.gov.ph as of 8 October 2026.

Source

checked on 8 Oct 2026

Offshore windawarded

South Korea offshore wind fixed-price contract tender, first half 2026

South Korea · Korea RPS fixed-price contract competitive bidding (wind)

Window
opens 30 Mar 2026
Awarded
30 Jun 2026
Authority
Ministry of Climate, Energy and Environment / Korea Energy Agency
Capacity / scope
1,800 MW tendered (1,400 MW fixed-bottom incl. 400 MW public-led, 400 MW floating); 1,786 MW selected

Tender notice published 30 March 2026; awarded on 30 June 2026, when the ministry reported five projects totalling 1,786 MW selected and pointed to a multi-year tender roadmap.

Source

checked on 8 Oct 2026

Offshore windannounced

Japan offshore wind operator tender, Round 4 (Hokkaido Matsumae and Hiyama promotion zones)

Japan · Japan Marine Renewable Energy Act operator tenders

Window
not published
Award expected
not published
Authority
METI / MLIT
Capacity / scope
not published

METI lists Hokkaido Matsumae and Hokkaido Hiyama as zones with pre-tender information provision; no tender start date is published, and no date for re-tendering the returned Round 1 zones was found.

Source

checked on 8 Oct 2026

After an award: the usual order of work

General sequence, not a forecast for any round listed here.

  • Offshore wind. Site award → developer's engineering and contracting → fabrication of foundations, cables and turbines → offshore installation → commissioning.
  • Grid & HVDC. Framework or platform award → detailed engineering → fabrication of jackets, topsides and cables → transport and installation → commissioning.
  • Oil & gas licensing. Licence award → seismic and exploration drilling → appraisal → field development decision → engineering, fabrication and installation, if a discovery is developed.
  • CCS & hydrogen. Support or licence award → final investment decision → engineering → construction → commissioning.