Project · Deepwater FPSO · Angola

Kaminho FPSO (Cameia & Golfinho)

TotalEnergies' seventh Angolan FPSO and the first large deepwater development in the Kwanza basin; TotalEnergies expects over 10 million man-hours of work in Angola.

Checked by hand against the sources below (2026-10-20).

  1. Engineering (done)
  2. Fabrication (now)
  3. Transport & installation (next)
  4. Hook-up
  5. Commissioning
  6. Operation

Now Fabrication (reported: FPSO conversion and subsea fabrication (execution since FID May 2024))

Next Transport & installation · not announced

Roles Project management & controls · Construction & supervision · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.

Later Operation 2028 (first oil target 2028, as reported)

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • TotalEnergiesOperator / owneroperator 40%; partners Petronas 40%, Sonangol 20%
  • SaipemEPC / main contractorthree contracts totalling US$3.7 bn (May 2024): EPC, transportation and commissioning of the Kaminho FPSO (VLCC conversion); 12-year FPSO operation and…
Kind
Deepwater FPSO
Country
Angola
Size
70,000 b/d FPSO; ~30 km subsea lines; first oil 2028
Operator
TotalEnergies
Position
9.60°S 12.40°E, approximate

Sources

  1. Angola: TotalEnergies launches the Kaminho deepwater projectTotalEnergies (company newsroom) · published 2024-05-21 · read 2026-10-20
  2. TotalEnergies launches Kaminho oil project offshore Angola, Saipem to supply, operate FPSOOffshore Magazine · published 2024-05-21 · read 2026-09-22
  3. Saipem secures $3.7 billion contracts for TotalEnergies' Kaminho project offshore AngolaWorld Oil · published 2024-05-21 · read 2026-09-22
  4. TotalEnergies plans $10 billion Angola investment with partners over five years, CEO says (Reuters)CNBC Africa · published 2026-09-10 · read 2026-10-08