Project · Offshore wind · United Kingdom

Inch Cape offshore wind farm

United Kingdom, North Sea.

From the public registers below, read 2026-10-24; only what they say.

  1. Engineering (done)
  2. Fabrication (done)
  3. Transport & installation (now)
  4. Hook-up (next)
  5. Commissioning
  6. Operation

Now Transport & installation (reported: Construction work announced to mariners: 5 notices, 4 Mar 2026 to 1 Dec 2026. Under Construction per Crown Estate Scotland)

Next Hook-up · not announced

Roles Construction & supervision · Commissioning & start-up · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • ICOLOperator / owneroperator (Global Wind Power Tracker)
  • Red Rock PowerOperator / ownerowner (Global Wind Power Tracker)
  • ESB GroupOperator / ownerowner (Global Wind Power Tracker)

Who else needs construction people in Northwest Europe

May 2027 is busier than usual here: 56 projects and stops in this phase, against a typical 25.5 a month.

46Oct 2026381513Jan 2027162336Apr 2027565346Jul 20274034
announced projectsplanned stopstypical phase length, not announcedas of 2026-10-24
How we count

Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.

Reserve people now

Kind
Offshore wind
Country
United Kingdom
Size
1080 MW
Operator
ICOL
Position
56.50°N 2.19°W, approximate

Sources

  1. Inch Cape Offshore Wind Farm - Under ConstructionCrown Estate Scotland - Offshore Wind · published 2026-10-21 · read 2026-10-24
  2. Inch Cape - construction (page of 2026-02-05)Global Wind Power Tracker, Global Energy Monitor (CC BY 4.0) · published 2026-02-05 · read 2026-10-24
  3. Notice KF-5732: Foundation Transition Piece Installation - Inch Cape site boundary (4 Mar 2026 to 30 Nov 2026)Kingfisher Information Service · published 2026-03-05
  4. Notice KF-5955: Construction Support Activities - Inch Cape (13 May 2026 to 1 Dec 2026)Kingfisher Information Service · published 2026-09-17
  5. Notice KF-6126: Inch Cape Inter Array Cable Installation Operations (8 Jul 2026 to 31 Oct 2026)Kingfisher Information Service · published 2026-09-17
  6. Notice KF-6282: Inch Cape site boundary - Jacket Foundation Pin Pile Installation (28 Aug 2026 to 31 Oct 2026)Kingfisher Information Service · published 2026-08-28