Project · Fabrication yard · Netherlands

Heerema Vlissingen - 2GW jacket fabrication

Fabricating jackets for IJmuiden Ver Beta, IJmuiden Ver Gamma and Nederwiek 2 under the GE Vernova-Seatrium consortium contract; Beta jacket construction under way (started Sept 2024); Gamma jacket construction started with ceremonial first steel cut, sail-out targeted summer 2028; each jacket ~10,000 tonnes, ~100m x…

As reported by the source below (2026-09-19).

  1. Engineering (done)
  2. Fabrication (now)
  3. Construction (next)
  4. Hook-up
  5. Commissioning
  6. Operation

Now Fabrication (reported: under construction)

Next Construction · summer 2028 (Gamma jacket sail-out targeted summer 2028, as reported)

Roles Project management & controls · Construction & supervision · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

Who else needs construction people in Northwest Europe

May 2027 is busier than usual here: 55 projects and stops in this phase, against a typical 24.5 a month.

45Oct 2026371412Jan 2027152235Apr 2027555245Jul 20273933
announced projectsplanned stopstypical phase length, not announcedas of 2026-10-24
How we count

Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.

Reserve people now

Kind
Fabrication yard
Country
Netherlands
Operator
TenneT
Position
51.44°N 3.75°E, as published

Sources

  1. Heerema Vlissingen - 2GW jacket fabrication - source pagereNEWS / Offshore Wind (2026) · read 2026-09-19