Offshore wind farm
IJmuiden Ver Alpha & Beta wind farms
Every fact below is as reported by the linked source, read on 19 Sep 2026. A field the source does not give says “not published”.
- Kind
- Offshore wind farm
- Capacity
- 4,000 MW
- Phase / status
- Planned
- Developer / operator
- Noordzeker (SSE Renewables, ABP, AGP) - Alpha; Zeevonk II (Copenhagen Infrastructure Partners, Vattenfall) - Beta
- Contractors
- not published
What’s next as of 19 Sep 2026
Development permits awarded 2024. Alpha (Noordzeker) commissioning targeted 2029. Beta (Zeevonk II) permit amended August 2025 to a two-phase build - first 1GW phase targeted 2029, second 1GW phase targeted 2032; TenneT's Beta grid platform jacket construction (first steel) began September 2025, sail-out from Vlissingen targeted summer 2027.
Source retrieved 19 Sep 2026
RVO.nl / Global Energy Monitor (2026) · retrieved 19 Sep 2026 · Public information, fact reported with source