The North Sea, live · Projects
Offshore grid platform
IJmuiden Ver Beta
Every fact below is as reported by the linked source, read on 19 Sep 2026. A field the source does not give says “not published”.
- Kind
- Offshore grid platform
- Capacity
- 2,000 MW
- Phase / status
- Under construction
- Operator
- TenneT
- Contractors
- GE Vernova-Seatrium consortium; jacket fabrication by Heerema Fabrication Group, Vlissingen
- Technology
- HVDC 525kV, 2GW programme
What’s next as of 19 Sep 2026
Jacket construction under way at Heerema Vlissingen since first steel cut September 2025 (first 1,700-tonne section raised August 2026); jacket sail-out targeted summer 2027, offshore installation 2027, topside installation H2 2028; commissioning targeted 2028.
Source retrieved 19 Sep 2026
Offshore Wind (Aug 2026) · retrieved 19 Sep 2026 · Public information, fact reported with source