Offshore grid platform

IJmuiden Ver Beta

Every fact below is as reported by the linked source, read on 19 Sep 2026. A field the source does not give says “not published”.

Kind
Offshore grid platform
Capacity
2,000 MW
Phase / status
Under construction
Operator
TenneT
Contractors
GE Vernova-Seatrium consortium; jacket fabrication by Heerema Fabrication Group, Vlissingen
Technology
HVDC 525kV, 2GW programme

What’s next as of 19 Sep 2026

Jacket construction under way at Heerema Vlissingen since first steel cut September 2025 (first 1,700-tonne section raised August 2026); jacket sail-out targeted summer 2027, offshore installation 2027, topside installation H2 2028; commissioning targeted 2028.

Source retrieved 19 Sep 2026

Offshore Wind (Aug 2026) · retrieved 19 Sep 2026 · Public information, fact reported with source