Offshore grid platform

IJmuiden Ver Alpha

Every fact below is as reported by the linked source, read on 20 Sep 2026. A field the source does not give says “not published”.

Kind
Offshore grid platform
Capacity
2,000 MW
Phase / status
Under construction
Operator
TenneT
Contractors
Hitachi Energy / Larsen & Toubro (HVDC converter stations; L&T replaced Petrofac in the consortium, reported 31 Oct 2025)
Technology
HVDC 525kV, 2GW programme

What’s next as of 20 Sep 2026

Onshore land station under construction (first Dutch 2GW-standard substation); commissioning targeted for 2029 per TenneT's 2GW programme schedule.

Source retrieved 20 Sep 2026

Splash247 (31 Oct 2025) · retrieved 20 Sep 2026 · Public information, fact reported with source