  1. Transport & installation

    Fengmiao 1 offshore wind farm

    Offshore wind · Taiwan

    transport, installation and burial of 33 inter-array cables (~64 km) using cable-lay vessel Nexus, starting 2027

    1. Engineering (done)
    2. Fabrication (done)
    3. Transport & installation (now)
    4. Hook-up
    5. Commissioning (next)
    6. Operation

    Next Commissioning, not announced

    Source: Offshore Magazine, 2025-01-14

  2. Other role

    Malmporten Project

    Port & marine works · Sweden

    cutter suction dredging contract

    1. Engineering (now)
    2. Fabrication (next)
    3. Construction
    4. Hook-up
    5. Commissioning
    6. Operation

    Next Fabrication, not announced

    Source: Van Oord, 2026-07-02

  3. Other role

    Roberts Bank Terminal 2

    Port & marine works · Canada

    cutter suction dredging works

    1. Engineering (now)
    2. Fabrication (next)
    3. Construction
    4. Hook-up
    5. Commissioning
    6. Operation

    Next Fabrication, not announced

    Source: Van Oord, 2026-07-15