Offshore windpostponed
Philippines Green Energy Auction 5 (fixed-bottom offshore wind)
Philippines · Green Energy Auction Program (GEA)
- Window
- 2 Mar 2026 – 1 Dec 2026
- Award expected
- not published
- Authority
- Department of Energy (DOE)
- Capacity / scope
- 3,300 MW (delivery 2028-2030)
Launched 25 November 2025, supplier registration began 2 March 2026; DOE announced on 10 July 2026 that auction activities were temporarily on hold for a recalibration review. DOE's indicative timeline of 29 July 2026: department circular signed by 24 August and published early September; supplemental TOR released by 2 October 2026; qualified-bidder posting through Q4 2026; Auction Proper 1 December 2026; bid validation to certificates of award 2 December 2026 - 30 June 2027. DOE says all dates are indicative; no resumption notice or supplemental TOR found on doe.gov.ph as of 8 October 2026.