Project · Process plant · Czechia
ZEVO Vráto waste-to-energy plant
New waste-to-energy facility with design, construction, equipment delivery, installation, commissioning and testing in the awarded scope. HOCHTIEF CZ, INVELT SERVIS and G-Team are named in the official result.
Checked by hand against the sources below (2026-11-08).
- Engineering (next)
- Fabrication
- Construction
- Hook-up
- Commissioning
- Operation
Now Before engineering (reported: Design-and-build award published 5 May 2026; physical construction progress not verified.)
Next Engineering · not announced
Roles Project management & controls · Engineering & design · Document control & support · Role groups per phase: our planning assumption from the Crew Forecast model.
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- ZEVO VrátoOperator / ownerowner / client
- HOCHTIEF CZOther roleaward consortium member
- INVELT SERVISOther roleaward consortium member
Contract awards public notices that name this project
ZEVO Vráto
Refuse-incineration plant construction work
- Buyer
- ZEVO Vráto, a.s.
- Value
- CZK 7,656,451,060 total for 3 winners
Work type, our reading Construction & supervision
- Kind
- Process plant
- Country
- Czechia
- Operator
- ZEVO Vráto
- Position
- country only
Sources
- Official award notice 307161-2026TED, Tenders Electronic Daily (EU) · published 2026-05-05 · read 2026-11-08