Project · Fabrication yard · Netherlands

Sif Maasvlakte 2 monopile mega-factory

Ramp-up completed: reached its planned output of 4-5 monopiles/week during H1 2026 and delivered 59 monopiles in Q2 2026, close to its ~60/quarter target; annual target ~200 monopiles once at full capacity.

As reported by the source below (2026-09-19).

  1. Engineering (done)
  2. Fabrication (done)
  3. Construction (done)
  4. Hook-up (done)
  5. Commissioning (done)
  6. Operation (now)

Now Operation (reported: operational)