Project · LNG · Qatar

North Field West LNG

Two more LNG trains of 8 MTPA for QatarEnergy, a copy of North Field South, with carbon capture.

Checked by hand against the sources below (2026-10-23).

  1. Engineering (now)
  2. Fabrication (next)
  3. Construction
  4. Hook-up
  5. Commissioning
  6. Operation

Now Engineering (reported: engineering (EPCC awarded 25 February 2026))

Next Fabrication · not announced

Roles Project management & controls · Construction & supervision · QA/QC & HSE · Document control & support · Role groups per phase: our planning assumption from the Crew Forecast model.

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • Technip EnergiesEPC / main contractorEPCC contractor, leader of the joint venture with CCC and GAC (awarded 25 February 2026, 'major': above EUR 1 billion)
  • CCCEPC / main contractorEPCC joint-venture partner
  • GACEPC / main contractorEPCC joint-venture partner
Kind
LNG
Country
Qatar
Size
2 trains of 8 MTPA (16 MTPA), plus 1.1 MTPA CO2 capture
Operator
QatarEnergy
Position
country only

Sources

  1. Technip Energies awarded major LNG contract for North Field West projectTechnip Energies · published 2026-02-25 · read 2026-10-23