Project · LNG · Oman
Marsa LNG
LNG bunkering plant at Sohar for TotalEnergies (80%) and OQ (20%).
Checked by hand against the sources below (2026-10-23).
- Engineering (done)
- Fabrication (done)
- Construction (now)
- Hook-up
- Commissioning (next)
- Operation
Now Construction (reported: construction, more than 55% complete at the end of June 2026)
Next Commissioning · not announced
Roles Commissioning & start-up · QA/QC & HSE · Project management & controls · Role groups per phase: our planning assumption from the Crew Forecast model.
Later Operation Q1 2028 (start-up Q1 2028, as reported)
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- TotalEnergiesOperator / owneroperator (80%, with OQ 20%)
- OQOther rolepartner (20%)
- Technip EnergiesEPC / main contractorEPC contractor for the 1 MTPA liquefaction train (awarded 22 April 2024, 'substantial')
- Kind
- LNG
- Country
- Oman
- Size
- 1 MTPA electric-drive LNG train and LNG bunkering
- Operator
- TotalEnergies
- Position
- country only
Sources
- Technip Energies awarded a substantial contract by TotalEnergies and OQ for Marsa LNGTechnip Energies · published 2024-04-22 · read 2026-10-23
- Marsa LNG storage tank nears completionOman Observer · published 2026-09-08 · read 2026-10-23