Project · LNG · Oman

Marsa LNG

LNG bunkering plant at Sohar for TotalEnergies (80%) and OQ (20%).

Checked by hand against the sources below (2026-10-23).

  1. Engineering (done)
  2. Fabrication (done)
  3. Construction (now)
  4. Hook-up
  5. Commissioning (next)
  6. Operation

Now Construction (reported: construction, more than 55% complete at the end of June 2026)

Next Commissioning · not announced

Roles Commissioning & start-up · QA/QC & HSE · Project management & controls · Role groups per phase: our planning assumption from the Crew Forecast model.

Later Operation Q1 2028 (start-up Q1 2028, as reported)

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • OQOther rolepartner (20%)
  • Technip EnergiesEPC / main contractorEPC contractor for the 1 MTPA liquefaction train (awarded 22 April 2024, 'substantial')
Kind
LNG
Country
Oman
Size
1 MTPA electric-drive LNG train and LNG bunkering
Operator
TotalEnergies
Position
country only

Sources

  1. Technip Energies awarded a substantial contract by TotalEnergies and OQ for Marsa LNGTechnip Energies · published 2024-04-22 · read 2026-10-23
  2. Marsa LNG storage tank nears completionOman Observer · published 2026-09-08 · read 2026-10-23