Project · Oil & gas, offshore · Norway

Irpa field development

gas field, Norwegian sea. Main supply base: not announced.

From the public registers below, read 2026-10-24; only what they say.

  1. Engineering (done)
  2. Fabrication (done)
  3. Transport & installation (now)
  4. Hook-up (next)
  5. Commissioning
  6. Operation

Now Transport & installation (reported: Approved for production (Sodir field status, updated 24 Feb 2026); facilities Irpa (installation))

Next Hook-up · not announced

Roles Construction & supervision · Commissioning & start-up · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.

Need people for this?Follow

Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →

Who works on it as the sources name them

  • EquinorOperator / owneroperator (Sodir)

Who else needs construction people in Northwest Europe

May 2027 is busier than usual here: 56 projects and stops in this phase, against a typical 25.5 a month.

46Oct 2026381513Jan 2027162336Apr 2027565346Jul 20274034
announced projectsplanned stopstypical phase length, not announcedas of 2026-10-24
How we count

Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.

Reserve people now

Kind
Oil & gas, offshore
Country
Norway
Operator
Equinor
Position
67.03°N 5.31°E, approximate

Sources

  1. Field Irpa - Approved for productionSodir FactPages · published 2026-02-24 · read 2026-10-24