Project · Offshore wind · Poland
Baltica II offshore wind farm
Poland, Baltic Sea. Planned start of operation (Global Wind Power Tracker, page of 2026-02-05): 2027.
From the public registers below, read 2026-10-24; only what they say.
- Engineering (done)
- Fabrication (done)
- Transport & installation (now)
- Hook-up (next)
- Commissioning
- Operation
Now Transport & installation (reported: All 111 monopiles installed (Energy Global, 24 Aug 2026))
Next Hook-up · not announced
Roles Construction & supervision · Commissioning & start-up · QA/QC & HSE · Role groups per phase: our planning assumption from the Crew Forecast model.
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- ØrstedOperator / ownerowner (Global Wind Power Tracker)
- PGE Energia OdnawialnaOperator / ownerowner (Global Wind Power Tracker)
Who else needs construction people in Northwest Europe
May 2027 is busier than usual here: 56 projects and stops in this phase, against a typical 25.5 a month.
How we count
Counted from the project database (sources on each project page) and planned power-station stops (Nord Pool UMM, Elexon, Elia). Announced: the phase falls in the month by announced dates, or a stop's own dates. Typical: only the start is known, so the project counts for at most the typical length of that phase for its type (Crew Forecast model). Operation is not counted. Role groups per phase are our planning assumption. Counts, not people.
- Kind
- Offshore wind
- Country
- Poland
- Size
- 1500 MW
- Operator
- Ørsted
- Position
- 55.07°N 17.10°E, approximate
Sources
- 111 Baltica 2 foundations completed on scheduleEnergy Global · published 2026-08-24 · read 2026-10-23
- Baltica II - pre-construction (page of 2026-02-05)Global Wind Power Tracker, Global Energy Monitor (CC BY 4.0) · published 2026-02-05 · read 2026-10-24