Project · CCS · Netherlands
Aramis CO2 transport & storage
Dutch government committed EUR 726m after Shell and TotalEnergies scaled back their planned funding; final investment decision by Gasunie/EBN expected in 2026; storage (22 Mt/year capacity) targeted operational by 2030. Designed to complement Porthos, using Porthos's onshore compressor station.
As reported by the source below (2026-09-19).
- Engineering (next)
- Fabrication
- Transport & installation
- Hook-up
- Commissioning
- Operation
Now Before engineering (reported: planned)
Next Engineering · not announced
Roles Project management & controls · Engineering & design · Document control & support · Role groups per phase: our planning assumption from the Crew Forecast model.
Later Operation 2030 (storage targeted operational by 2030, as reported)
Their rate stays; our fee goes on top: 20% → 15% → 12%. Open book →
Who works on it as the sources name them
- TotalEnergiesOther roledevelop
- ShellOther roledevelop
- Kind
- CCS
- Country
- Netherlands
- Operator
- Gasunie
- Position
- 51.93°N 4.03°E, approximate
On the Radar each linked to its source
Sources
- Aramis CO2 transport & storage - source pageGasunie / gasworld (2026) · read 2026-09-19
- Aramis: second CO2 transport and storage system for RotterdamTotalEnergies · published 2026-09-18 · read 2026-10-23