BEGIN:VCALENDAR
VERSION:2.0
PRODID:-//YRproject//Tender calendar//EN
CALSCALE:GREGORIAN
METHOD:PUBLISH
X-WR-CALNAME:Energy & offshore tender calendar 2026–2028
BEGIN:VEVENT
UID:tw-offshore-wind-round-3-3-window-open@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20260401
DTEND;VALUE=DATE:20260402
SUMMARY:Taiwan offshore wind zonal development\, Round 3.3 capacity allocat
 ion — window opens
DESCRIPTION:Applications accepted 1 April to 30 September 2026\; the minist
 ry plans to complete selection and publish results before the end of 2026\
 ; grid connection 2030-2031. Trade press (UDN\, 30 Sep 2026) reports the E
 nergy Administration received two applications for two wind farms (CIP and
  Orsted)\, well short of the 3.6 GW on offer\; no ministry release on the 
 receipt count was found. Authority: Ministry of Economic Affairs / Energy 
 Administration. Date as published by the authority\; checked on 2026-10-08
 . Always check the source: https://investtaiwan.nat.gov.tw/newsPage98905ch
 t?lang=cht&search=98905
URL:https://investtaiwan.nat.gov.tw/newsPage98905cht?lang=cht&search=98905
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:tw-offshore-wind-round-3-3-window-close@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20260930
DTEND;VALUE=DATE:20261001
SUMMARY:Taiwan offshore wind zonal development\, Round 3.3 capacity allocat
 ion — window closes
DESCRIPTION:Applications accepted 1 April to 30 September 2026\; the minist
 ry plans to complete selection and publish results before the end of 2026\
 ; grid connection 2030-2031. Trade press (UDN\, 30 Sep 2026) reports the E
 nergy Administration received two applications for two wind farms (CIP and
  Orsted)\, well short of the 3.6 GW on offer\; no ministry release on the 
 receipt count was found. Authority: Ministry of Economic Affairs / Energy 
 Administration. Date as published by the authority\; checked on 2026-10-08
 . Always check the source: https://investtaiwan.nat.gov.tw/newsPage98905ch
 t?lang=cht&search=98905
URL:https://investtaiwan.nat.gov.tw/newsPage98905cht?lang=cht&search=98905
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ph-gea-5-offshore-wind-window-open@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20260302
DTEND;VALUE=DATE:20260303
SUMMARY:Philippines Green Energy Auction 5 (fixed-bottom offshore wind) —
  window opens
DESCRIPTION:Launched 25 November 2025\, supplier registration began 2 March
  2026\; DOE announced on 10 July 2026 that auction activities were tempora
 rily on hold for a recalibration review. DOE's indicative timeline of 29 J
 uly 2026: department circular signed by 24 August and published early Sept
 ember\; supplemental TOR released by 2 October 2026\; qualified-bidder pos
 ting through Q4 2026\; Auction Proper 1 December 2026\; bid validation to 
 certificates of award 2 December 2026 - 30 June 2027. DOE says all dates a
 re indicative\; no resumption notice or supplemental TOR found on doe.gov.
 ph as of 8 October 2026. Authority: Department of Energy (DOE). Date as pu
 blished by the authority\; checked on 2026-10-08. Always check the source:
  https://doe.gov.ph/news/press-releases/3345934--doe-announces-the-timelin
 e-of-activities-for-the-fifth-auction-round-of-the-green-energy-auction-pr
 ogram-gea-5-
URL:https://doe.gov.ph/news/press-releases/3345934--doe-announces-the-timel
 ine-of-activities-for-the-fifth-auction-round-of-the-green-energy-auction-
 program-gea-5-
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:ph-gea-5-offshore-wind-window-close@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20261201
DTEND;VALUE=DATE:20261202
SUMMARY:Philippines Green Energy Auction 5 (fixed-bottom offshore wind) —
  window closes
DESCRIPTION:Launched 25 November 2025\, supplier registration began 2 March
  2026\; DOE announced on 10 July 2026 that auction activities were tempora
 rily on hold for a recalibration review. DOE's indicative timeline of 29 J
 uly 2026: department circular signed by 24 August and published early Sept
 ember\; supplemental TOR released by 2 October 2026\; qualified-bidder pos
 ting through Q4 2026\; Auction Proper 1 December 2026\; bid validation to 
 certificates of award 2 December 2026 - 30 June 2027. DOE says all dates a
 re indicative\; no resumption notice or supplemental TOR found on doe.gov.
 ph as of 8 October 2026. Authority: Department of Energy (DOE). Date as pu
 blished by the authority\; checked on 2026-10-08. Always check the source:
  https://doe.gov.ph/news/press-releases/3345934--doe-announces-the-timelin
 e-of-activities-for-the-fifth-auction-round-of-the-green-energy-auction-pr
 ogram-gea-5-
URL:https://doe.gov.ph/news/press-releases/3345934--doe-announces-the-timel
 ine-of-activities-for-the-fifth-auction-round-of-the-green-energy-auction-
 program-gea-5-
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:kr-offshore-wind-fixed-price-2026-h1-window-open@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20260330
DTEND;VALUE=DATE:20260331
SUMMARY:South Korea offshore wind fixed-price contract tender\, first half 
 2026 — window opens
DESCRIPTION:Tender notice published 30 March 2026\; awarded on 30 June 2026
 \, when the ministry reported five projects totalling 1\,786 MW selected a
 nd pointed to a multi-year tender roadmap. Authority: Ministry of Climate\
 , Energy and Environment / Korea Energy Agency. Date as published by the a
 uthority\; checked on 2026-10-08. Always check the source: https://www.kor
 ea.kr/briefing/pressReleaseView.do?newsId=156751585
URL:https://www.korea.kr/briefing/pressReleaseView.do?newsId=156751585
TRANSP:TRANSPARENT
END:VEVENT
BEGIN:VEVENT
UID:kr-offshore-wind-fixed-price-2026-h1-award-expected@yrproject.nl
DTSTAMP:20261008T000000Z
DTSTART;VALUE=DATE:20260630
DTEND;VALUE=DATE:20260701
SUMMARY:South Korea offshore wind fixed-price contract tender\, first half 
 2026 — awarded
DESCRIPTION:Tender notice published 30 March 2026\; awarded on 30 June 2026
 \, when the ministry reported five projects totalling 1\,786 MW selected a
 nd pointed to a multi-year tender roadmap. Authority: Ministry of Climate\
 , Energy and Environment / Korea Energy Agency. Date as published by the a
 uthority\; checked on 2026-10-08. Always check the source: https://www.kor
 ea.kr/briefing/pressReleaseView.do?newsId=156751585
URL:https://www.korea.kr/briefing/pressReleaseView.do?newsId=156751585
TRANSP:TRANSPARENT
END:VEVENT
END:VCALENDAR